710 S WESTERN AVE 90005

Certificate Information: 710 S WESTERN AVE 90005

Application / Permit
23014-10000-03767
Plan Check / Job No.
B23LA17420
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
****ePlan**** new freezer addition to (e) restaurant (270 SF)
Permit Issued
Issued on 7/24/2024
Issuing Office
Current Status
CofO Issued on 5/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2023 APPLICANT
Assigned to Plan Check Engineer 9/28/2023 REZA HAGHIGHAT
Corrections Issued 10/1/2023 REZA HAGHIGHAT
Quality Review Completed 10/5/2023 KAVIAN REFAHI
Applicant returned to address corrections 4/3/2024 REZA HAGHIGHAT
Applicant returned to address corrections 6/13/2024 REZA HAGHIGHAT
Plan Check Approved 7/20/2024 REZA HAGHIGHAT
Issued 7/24/2024 APPLICANT
CofO in Progress 5/7/2025 LARRY ARNICK
Permit Finaled 5/14/2025 ERNESTO CORRAL
CofO Issued 5/14/2025 ERNESTO CORRAL
Permit Finaled 5/14/2025 ERNESTO CORRAL

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/3/2023 AMBER CAMPBELL
Sewer availability Cleared 11/3/2023 AMBER CAMPBELL
Redevelopment Project Area Cleared 11/15/2023 DAVID URITA
ZA Case Cleared 11/15/2023 DAVID URITA
Eng Process Fee Ord 176,300 Cleared 11/16/2023 AMBER CAMPBELL
DAS Clearance Cleared 4/18/2024 Lawrence Quirante
Green Code Cleared 4/23/2024 Lawrence Quirante
Food Service Establishment Cleared 4/25/2024 PAWAN VERMA
Food establishment approval Cleared 6/13/2024 LACDHS APPROVED

Contact Information

Contractor Cal Future Construction Inc; Lic. No.: 1061199-B       ,
Engineer Hwang,, Junho; Lic. No.: S5592 815 FAIRVIEW AVE #205      SOUTH PASADENA, CA 91030

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Barrier 8/7/2024 Partial Approval JEROME BLACKWOOD
METHANE-Subgrade 8/7/2024 Partial Approval JEROME BLACKWOOD
Deputy Methane Barrier 8/8/2024 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 8/22/2024 Approved JACOB MYERS
Excavation/Setback/Form/Re-Bar 8/27/2024 Partial Approval JEROME BLACKWOOD
Green Building Rough 9/17/2024 Not Ready for Inspection JEROME BLACKWOOD
METHANE-Rough 9/17/2024 Approved JEROME BLACKWOOD
Wood Frame 9/17/2024 Not Ready for Inspection JEROME BLACKWOOD
Drywall Nailing 10/29/2024 Partial Inspection JEROME BLACKWOOD
Green Building Rough 10/29/2024 Not Ready for Inspection JEROME BLACKWOOD
Interior/Exterior Lathing 11/14/2024 Partial Approval JEROME BLACKWOOD
Drywall Nailing 2/3/2025 Approved JEROME BLACKWOOD
Final 2/3/2025 Not Ready for Inspection JEROME BLACKWOOD
Footing/Foundation/Slab 2/3/2025 Approved JEROME BLACKWOOD
Green Building Final 2/3/2025 Approved JEROME BLACKWOOD
Green Building Rough 2/3/2025 Approved JEROME BLACKWOOD
METHANE-Barrier 2/3/2025 Approved JEROME BLACKWOOD
METHANE-Subgrade 2/3/2025 Approved JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 2/3/2025 SGSOV Approved JEROME BLACKWOOD
Smoke Detectors 2/3/2025 Approved JEROME BLACKWOOD
Wood Frame 2/3/2025 Approved JEROME BLACKWOOD
Final 2/19/2025 Not Ready for Inspection JEROME BLACKWOOD
Final 4/22/2025 Not Ready for Inspection JEROME BLACKWOOD
Final 5/6/2025 OK to Issue CofO LARRY ARNICK