5300 N FORBES AVE 91436
Certificate Information: 5300 N FORBES AVE 91436
- Application / Permit
- 23014-10000-03742
- Plan Check / Job No.
- B23LA17272
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: (N) attached patio cover addtition to (E) single family dwelling per information bulletin P/BC 2020-006.
- Permit Issued
- Issued on 9/28/2023
- Issuing Office
- Current Status
- Issued on 9/28/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2023 | CAROLEAN BASMA |
| Corrections Issued | 9/18/2023 | CAROLEAN BASMA |
| Plan Check Approved | 9/25/2023 | DANIEL YIP |
| Issued | 9/28/2023 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/19/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/12/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2023 | Approved | SEAN HAUPT |
| Green Building Rough | 10/23/2023 | Approved | SEAN HAUPT |
| Wood Frame | 10/23/2023 | Partial Approval | SEAN HAUPT |
| Final | 11/15/2023 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 11/15/2023 | Approved | VINCENT HANLEY |
| Green Building Final | 11/15/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 11/15/2023 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 11/15/2023 | Approved | VINCENT HANLEY |
| Wood Frame | 11/15/2023 | Approved | VINCENT HANLEY |