5045 E RANGE VIEW AVE 90042

Certificate Information: 5045 E RANGE VIEW AVE 90042

Application / Permit
23014-10000-03737
Plan Check / Job No.
B23LA17236
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to (E) 1-story SFD with attached garage.
Permit Issued
Issued on 4/26/2024
Issuing Office
Current Status
Issued on 4/26/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/14/2023 APPLICANT
Assigned to Plan Check Engineer 9/28/2023 GEORGE JOLAKIAN
Corrections Issued 10/13/2023 GEORGE JOLAKIAN
Quality Review Completed 10/26/2023 RODOLFO ARIAS
Plan Check Approved 4/23/2024 GEORGE JOLAKIAN
Issued 4/26/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/23/2024 JEANIE LAM
Sewer availability Cleared 2/23/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/29/2024 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Zhuang,, Wenbin; Lic. No.: S5236 205 S CHAPEL AVE #D-1      ALHAMBRA, CA 91801

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/28/2024 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 9/12/2024 Corrections Issued ROY SPAULDING
Excavation/Setback/Form/Re-Bar 9/18/2024 Approved ROY SPAULDING
BUILDING-Rough-Frame 11/12/2024 Not Ready for Inspection ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 11/12/2024 Approved ROY SPAULDING
Green Building Rough 11/12/2024 Not Ready for Inspection ROY SPAULDING
Insulation 11/12/2024 Not Ready for Inspection ROY SPAULDING
Verify Sprinkler Sign Off 11/12/2024 Approved ROY SPAULDING
Wood Frame 11/12/2024 Not Ready for Inspection ROY SPAULDING
BUILDING-Rough-Frame 11/26/2024 Not Ready for Inspection WILLIAM SIERRA
Green Building Rough 11/26/2024 Not Ready for Inspection WILLIAM SIERRA
HVAC-Rough 11/26/2024 Corrections Issued WILLIAM SIERRA
Insulation 11/26/2024 Not Ready for Inspection WILLIAM SIERRA
BUILDING-Rough-Frame 12/4/2024 Approved ROY SPAULDING
ELECTRICAL-Rough 12/4/2024 Approved ROY SPAULDING
Green Building Rough 12/4/2024 Approved ROY SPAULDING
HVAC-Rough 12/4/2024 Approved ROY SPAULDING
PLUMBING-Rough 12/4/2024 Approved ROY SPAULDING
Wood Frame 12/4/2024 Approved ROY SPAULDING
Insulation 12/17/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 12/17/2024 Corrections Issued JOSH MEISTER
Drywall Nailing 12/23/2024 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 12/23/2024 Approved CHARLES BOGHOSKHAN
ELECTRICAL-Final 6/24/2025 Corrections Issued ALIZAH MAYAGOITIA
Final 6/24/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 6/24/2025 Approved ALIZAH MAYAGOITIA
Green Building Final 6/24/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 6/24/2025 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Final 6/24/2025 Corrections Issued ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 6/24/2025 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 6/24/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 7/31/2025 Approved DAVID WILLIAMS
Final 7/31/2025 Not Ready for Inspection DAVID WILLIAMS
Green Building Final 7/31/2025 Approved DAVID WILLIAMS
HVAC-Final 7/31/2025 Approved DAVID WILLIAMS
PLUMBING-Final 7/31/2025 Approved DAVID WILLIAMS
Verify Sprinkler Sign Off 7/31/2025 Approved DAVID WILLIAMS