5045 E RANGE VIEW AVE 90042
Certificate Information: 5045 E RANGE VIEW AVE 90042
- Application / Permit
- 23014-10000-03737
- Plan Check / Job No.
- B23LA17236
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to (E) 1-story SFD with attached garage.
- Permit Issued
- Issued on 4/26/2024
- Issuing Office
- Current Status
- Issued on 4/26/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2023 | GEORGE JOLAKIAN |
| Corrections Issued | 10/13/2023 | GEORGE JOLAKIAN |
| Quality Review Completed | 10/26/2023 | RODOLFO ARIAS |
| Plan Check Approved | 4/23/2024 | GEORGE JOLAKIAN |
| Issued | 4/26/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/23/2024 | JEANIE LAM |
| Sewer availability | Cleared | 2/23/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2024 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 205 S CHAPEL AVE #D-1 ALHAMBRA, CA 91801 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/28/2024 | Conditional Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/12/2024 | Corrections Issued | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 9/18/2024 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 11/12/2024 | Not Ready for Inspection | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Approved | ROY SPAULDING |
| Green Building Rough | 11/12/2024 | Not Ready for Inspection | ROY SPAULDING |
| Insulation | 11/12/2024 | Not Ready for Inspection | ROY SPAULDING |
| Verify Sprinkler Sign Off | 11/12/2024 | Approved | ROY SPAULDING |
| Wood Frame | 11/12/2024 | Not Ready for Inspection | ROY SPAULDING |
| BUILDING-Rough-Frame | 11/26/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| Green Building Rough | 11/26/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| HVAC-Rough | 11/26/2024 | Corrections Issued | WILLIAM SIERRA |
| Insulation | 11/26/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 12/4/2024 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 12/4/2024 | Approved | ROY SPAULDING |
| Green Building Rough | 12/4/2024 | Approved | ROY SPAULDING |
| HVAC-Rough | 12/4/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 12/4/2024 | Approved | ROY SPAULDING |
| Wood Frame | 12/4/2024 | Approved | ROY SPAULDING |
| Insulation | 12/17/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 12/17/2024 | Corrections Issued | JOSH MEISTER |
| Drywall Nailing | 12/23/2024 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 12/23/2024 | Approved | CHARLES BOGHOSKHAN |
| ELECTRICAL-Final | 6/24/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 6/24/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 6/24/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 6/24/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 6/24/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 6/24/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/24/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 6/24/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 7/31/2025 | Approved | DAVID WILLIAMS |
| Final | 7/31/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Green Building Final | 7/31/2025 | Approved | DAVID WILLIAMS |
| HVAC-Final | 7/31/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Final | 7/31/2025 | Approved | DAVID WILLIAMS |
| Verify Sprinkler Sign Off | 7/31/2025 | Approved | DAVID WILLIAMS |