6631 W 80TH PL 90045

Certificate Information: 6631 W 80TH PL 90045

Application / Permit
23014-10000-03735
Plan Check / Job No.
B23LA17231
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. INTERIOR REMODEL WITH ADDITION AND NEW COVERED PORCH TO (E) SFD. INCREASE IN HEIGHT OF SFD.
Permit Issued
Issued on 11/6/2023
Issuing Office
Current Status
CofO Issued on 1/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2023 APPLICANT
Assigned to Plan Check Engineer 9/20/2023 DAVID CASTILLO
Corrections Issued 9/21/2023 DAVID CASTILLO
Applicant returned to address corrections 11/1/2023 DAVID CASTILLO
Plan Check Approved 11/3/2023 JASON JANGADA
Plan Check Approved 11/4/2023 JASON JANGADA
Issued 11/6/2023 APPLICANT
CofO in Progress 1/9/2025 TEMISTOCLES CAAL
Permit Finaled 1/10/2025 RICHARD STEINBACH
CofO Issued 1/10/2025 RICHARD STEINBACH
Permit Finaled 1/10/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 9/28/2023 ALESSANDRO MERCURI
Roof/Waste drainage to street Cleared 10/24/2023 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 10/26/2023 DINAH GARIN

Contact Information

Contractor Everest Construct Inc; Lic. No.: 1075122-B       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/17/2023 No Access for Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 11/29/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 12/12/2023 Partial Approval BOBBY KEY
Wood Frame 12/12/2023 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/15/2023 Partial Approval BOBBY KEY
Insulation 12/15/2023 Partial Approval BOBBY KEY
ELECTRICAL-Rough 1/11/2024 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/11/2024 Partial Approval BOBBY KEY
PLUMBING-Rough 1/11/2024 Not Ready for Inspection BOBBY KEY
Footing/Foundation/Slab 1/17/2024 Approved RICHARD STEINBACH
Insulation 1/17/2024 Partial Approval RICHARD STEINBACH
PLUMBING-Rough 1/17/2024 Approved RICHARD STEINBACH
BUILDING-Rough-Frame 1/23/2024 Conditional Approval BOBBY KEY
Green Building Rough 1/23/2024 Not Ready for Inspection BOBBY KEY
HVAC-Rough 1/23/2024 Approved BOBBY KEY
Insulation 1/23/2024 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 1/23/2024 Approved BOBBY KEY
Excavation/Setback/Form/Re-Bar 1/24/2024 Approved BOBBY KEY
Insulation 1/24/2024 Approved BOBBY KEY
Interior/Exterior Lathing 1/24/2024 Partial Approval BOBBY KEY
Interior/Exterior Lathing 1/29/2024 Approved BOBBY KEY
Drywall Nailing 2/1/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/15/2024 SGSOV Approved JESUS PINEDA
Gas Test 5/17/2024 Corrections Issued TEMISTOCLES CAAL
Gas Test 5/21/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 12/16/2024 Approved TEMISTOCLES CAAL
Final 12/16/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 12/16/2024 Not Ready for Inspection TEMISTOCLES CAAL
Green Building Rough 12/16/2024 Approved TEMISTOCLES CAAL
Smoke Detectors 12/16/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 1/8/2025 Approved TEMISTOCLES CAAL
Final 1/8/2025 OK to Issue CofO TEMISTOCLES CAAL
Green Building Final 1/8/2025 Approved TEMISTOCLES CAAL
HVAC-Final 1/8/2025 Approved TEMISTOCLES CAAL
PLUMBING-Final 1/8/2025 Approved TEMISTOCLES CAAL