6631 W 80TH PL 90045
Certificate Information: 6631 W 80TH PL 90045
- Application / Permit
- 23014-10000-03735
- Plan Check / Job No.
- B23LA17231
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN. INTERIOR REMODEL WITH ADDITION AND NEW COVERED PORCH TO (E) SFD. INCREASE IN HEIGHT OF SFD.
- Permit Issued
- Issued on 11/6/2023
- Issuing Office
- Current Status
- CofO Issued on 1/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2023 | DAVID CASTILLO |
| Corrections Issued | 9/21/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 11/1/2023 | DAVID CASTILLO |
| Plan Check Approved | 11/3/2023 | JASON JANGADA |
| Plan Check Approved | 11/4/2023 | JASON JANGADA |
| Issued | 11/6/2023 | APPLICANT |
| CofO in Progress | 1/9/2025 | TEMISTOCLES CAAL |
| Permit Finaled | 1/10/2025 | RICHARD STEINBACH |
| CofO Issued | 1/10/2025 | RICHARD STEINBACH |
| Permit Finaled | 1/10/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 9/28/2023 | ALESSANDRO MERCURI |
| Roof/Waste drainage to street | Cleared | 10/24/2023 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2023 | DINAH GARIN |
Contact Information
| Contractor | Everest Construct Inc; Lic. No.: 1075122-B | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/17/2023 | No Access for Inspection | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 11/29/2023 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 12/12/2023 | Partial Approval | BOBBY KEY |
| Wood Frame | 12/12/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2023 | Partial Approval | BOBBY KEY |
| Insulation | 12/15/2023 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 1/11/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 1/11/2024 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 1/17/2024 | Approved | RICHARD STEINBACH |
| Insulation | 1/17/2024 | Partial Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 1/17/2024 | Approved | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 1/23/2024 | Conditional Approval | BOBBY KEY |
| Green Building Rough | 1/23/2024 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 1/23/2024 | Approved | BOBBY KEY |
| Insulation | 1/23/2024 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 1/23/2024 | Approved | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 1/24/2024 | Approved | BOBBY KEY |
| Insulation | 1/24/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/24/2024 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 1/29/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 2/1/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/15/2024 | SGSOV Approved | JESUS PINEDA |
| Gas Test | 5/17/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Gas Test | 5/21/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 12/16/2024 | Approved | TEMISTOCLES CAAL |
| Final | 12/16/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 12/16/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Green Building Rough | 12/16/2024 | Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 12/16/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 1/8/2025 | Approved | TEMISTOCLES CAAL |
| Final | 1/8/2025 | OK to Issue CofO | TEMISTOCLES CAAL |
| Green Building Final | 1/8/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 1/8/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 1/8/2025 | Approved | TEMISTOCLES CAAL |