414 N AVENUE 61 90042

Certificate Information: 414 N AVENUE 61 90042

Application / Permit
23014-10000-03726
Plan Check / Job No.
B23LA17189
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: IRREGULAR SHAPED REAR ADDITION AND REMODEL TO (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 8/7/2025
Issuing Office
Current Status
Issued on 8/7/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/4/2023 APPLICANT
Assigned to Plan Check Engineer 10/6/2023 LUISANGEL VALENZUELA
Corrections Issued 10/7/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 2/10/2025 ALEC MOUSAKHANIAN
Applicant returned to address corrections 7/16/2025 GIOVANNY CHAVEZ
Plan Check Approved 7/19/2025 LUISANGEL VALENZUELA
Issued 8/7/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 10/18/2023 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 10/26/2023 AMBER CAMPBELL
CPC Cleared 11/26/2024 JACQUELINE TORRES
HPOZ Cleared 1/27/2025 NATHALY DE LA PAZ
ZI Cleared 1/27/2025 NATHALY DE LA PAZ
Low Impact Development (LID) Cleared 7/1/2025 LUIS LUVANO
Roof/Waste drainage to street Cleared 7/12/2025 JEREMY CHOK
Grading Pre-Inspection Cleared 7/16/2025 LUISANGEL VALENZUELA

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/8/2025 Partial Inspection LILIANA PORTILLO
Pre-Inspection 9/24/2025 Partial Inspection LILIANA PORTILLO
PLUMBING-Rough 10/14/2025 Corrections Issued LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 10/22/2025 Approved DAVID WILLIAMS
Footing/Foundation/Slab 10/22/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 10/30/2025 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/26/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 12/22/2025 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 12/22/2025 Corrections Issued LILIANA PORTILLO
HVAC-Rough 12/22/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 12/22/2025 Corrections Issued LILIANA PORTILLO
Insulation 3/11/2026 Corrections Issued GEM DE OCAMPO
Shower Pan 3/11/2026 Approved GEM DE OCAMPO
ELECTRICAL-Rough 3/16/2026 Approved LILIANA PORTILLO
HVAC-Rough 3/16/2026 Approved LILIANA PORTILLO
PLUMBING-Rough 3/16/2026 Approved LILIANA PORTILLO
Drywall Nailing 3/25/2026 Approved GEM DE OCAMPO
Green Building Rough 3/25/2026 Approved GEM DE OCAMPO
Insulation 3/25/2026 Approved GEM DE OCAMPO
Interior/Exterior Lathing 3/25/2026 Partial Approval GEM DE OCAMPO
Interior/Exterior Lathing 6/2/2026 Approved OSVALDO PARAMO