3634 S VETERAN AVE 90034

Certificate Information: 3634 S VETERAN AVE 90034

Application / Permit
23014-10000-03725
Plan Check / Job No.
B23LA17179
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* CONVERT (E) DETACHED 2-CAR GARAGE TO ADU, GROUND FLOOR ADDITION, AND SECOND FLOOR ADDITION TO ADU PER LAMC 12.22A.33(c)-(d).
Permit Issued
Issued on 4/30/2025
Issuing Office
Current Status
Issued on 4/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/15/2023 APPLICANT
Assigned to Plan Check Engineer 9/28/2023 VIVIAN LAO
Corrections Issued 9/29/2023 VIVIAN LAO
Quality Review Completed 10/3/2023 GARO TELMI
Applicant returned to address corrections 1/30/2024 VIVIAN LAO
Applicant returned to address corrections 3/14/2024 VIVIAN LAO
Applicant returned to address corrections 5/9/2024 VIVIAN LAO
Applicant returned to address corrections 9/30/2024 VIVIAN LAO
Plan Check Approved 3/12/2025 VIVIAN LAO
Issued 4/30/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/9/2024 VIVIAN LAO
Address approval Cleared 5/20/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 5/23/2024 DARIN LAM
Sewer availability Cleared 5/23/2024 DARIN LAM
Specific Plan Cleared 6/26/2024 FREDDY GARCIA
GPI Written Notices Cleared 9/30/2024 VIVIAN LAO
Low Impact Development (LID) Cleared 1/28/2025 MITESH PATEL
Roof/Waste drainage to street Cleared 2/22/2025 LIAM ODONOVAN
Miscellaneous Cleared 2/28/2025 KIMBERLY HERNANDEZ

Contact Information

Contractor Y W Rising Builders Inc; Lic. No.: 1006010-B       ,
Contractor Ywr Fire Protection; Lic. No.: 1006010-B       ,
Engineer Gao,, Jianfeng; Lic. No.: C88478 18825 ELMHURST ST      ROWLAND HEIGHTS, CA 91748

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/9/2025 Approved KIRK SANDERS
PLUMBING-Rough 10/2/2025 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 11/10/2025 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/26/2026 Partial Approval RYAN SALAZAR
Green Building Rough 3/26/2026 Not Ready for Inspection RYAN SALAZAR
Wood Frame 3/26/2026 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 5/7/2026 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 5/7/2026 Not Ready for Inspection EUGENE CASSIDY