ePlan: ACCESSORY DWELLING UNIT ADDITION TO (E) GARAGE PER GC 66323(a)(2)
Permit Issued
Issued on 4/14/2025
Issuing Office
Current Status
CofO Issued on 2/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2023 APPLICANT
Assigned to Plan Check Engineer 9/21/2023 DANIEL YIP
Corrections Issued 9/27/2023 DANIEL YIP
Quality Review Completed 9/27/2023 GARO TELMI
Applicant returned to address corrections 1/19/2024 DANIEL YIP
Applicant returned to address corrections 9/20/2024 DANIEL YIP
Applicant returned to address corrections 11/15/2024 DANIEL YIP
Applicant returned to address corrections 12/18/2024 DANIEL YIP
Applicant returned to address corrections 1/27/2025 DANIEL YIP
Plan Check Approved 4/10/2025 DANIEL YIP
Issued 4/14/2025 APPLICANT
CofO in Progress 2/4/2026 JESUS PINEDA
Permit Finaled 2/5/2026 RICHARD STEINBACH
CofO Issued 2/5/2026 RICHARD STEINBACH
Permit Finaled 2/5/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 12/14/2023 CELINA MORENO
Roof/Waste drainage to street Cleared 12/15/2023 CELINA MORENO
Sewer availability Cleared 12/20/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/10/2024 JUSTIN BICOL
Specific Plan Cleared 1/30/2024 ALESSANDRO MERCURI
Construction near power lines Cleared 2/12/2024 RIDWAN HARDY

Contact Information

Architect Ottolia,, Domingo C; Lic. No.: C27790 5533 BAYRIDGE RD.      RANCHO PALOS VERDES, CA 90275
Contractor Valentine Construction; Lic. No.: 655063-B       ,
Engineer Bell,, William Andrew; Lic. No.: C88870 550 DEEP VALLEY DR STE 273      ROLLING HILLS ESTATES, CA 90274

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/23/2025 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 6/25/2025 Partial Approval TEMISTOCLES CAAL
Deputy Reinf. Concrete 7/1/2025 Conditional Approval DAVID FEILER
BUILDING-Rough-Frame 7/16/2025 Partial Approval ANTHONY EGSON
ELECTRICAL-Rough 7/16/2025 Partial Approval ANTHONY EGSON
Green Building Rough 7/16/2025 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 7/16/2025 Approved ANTHONY EGSON
Deputy Drilled-In Anchors 7/22/2025 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 7/23/2025 Corrections Issued JESUS PINEDA
Green Building Rough 7/23/2025 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Rough 8/13/2025 Approved RUBEN RIVAS
Green Building Rough 8/13/2025 Not Ready for Inspection RUBEN RIVAS
HVAC-Rough 8/13/2025 Corrections Issued RUBEN RIVAS
PLUMBING-Rough 8/13/2025 Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 8/26/2025 Partial Approval JESUS PINEDA
Sewer 8/26/2025 Approved JESUS PINEDA
Underground Mechanical 8/26/2025 Approved JESUS PINEDA
Deputy Wood Construction 9/11/2025 Conditional Approval JESUS PINEDA
BUILDING-Rough-Frame 9/12/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 9/12/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 10/1/2025 Approved JESUS PINEDA
Green Building Rough 10/1/2025 Approved JESUS PINEDA
HVAC-Rough 10/1/2025 Approved JESUS PINEDA
Insulation 10/1/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 10/1/2025 Partial Approval JESUS PINEDA
Special/Order Compliance 10/1/2025 Partial Inspection BOBBY KEY
Special/Order Compliance 10/1/2025 Partial Inspection HERBERT GIRON
Drywall Nailing 10/7/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 10/21/2025 Approved TEMISTOCLES CAAL
Shower Pan 10/21/2025 Approved TEMISTOCLES CAAL
Special/Order Compliance 10/21/2025 Partial Inspection BOBBY KEY
Special/Order Compliance 10/21/2025 Partial Inspection HERBERT GIRON
ELECTRICAL-Final 12/4/2025 Approved JESUS PINEDA
Final 12/4/2025 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 12/4/2025 Approved JESUS PINEDA
Green Building Final 12/4/2025 Corrections Issued JESUS PINEDA
HVAC-Final 12/4/2025 Approved JESUS PINEDA
PLUMBING-Final 12/4/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 12/4/2025 SGSOV Approved JESUS PINEDA
Smoke Detectors 12/4/2025 Approved JESUS PINEDA
Final 2/4/2026 OK to Issue CofO JESUS PINEDA
Green Building Final 2/4/2026 Approved JESUS PINEDA