500 W 148TH ST 90248

Certificate Information: 500 W 148TH ST 90248

Application / Permit
23014-10000-03686
Plan Check / Job No.
B23LA17008
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan PROP. ONE STORY ADDITION: (240 SQ. FT.) TO (E) SFD AND REMODEL
Permit Issued
Issued on 5/20/2024
Issuing Office
Current Status
Issued on 5/20/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/30/2023 APPLICANT
Assigned to Plan Check Engineer 11/1/2023 KHUONG TRUONG
Corrections Issued 11/2/2023 KHUONG TRUONG
Plan Check Approved 3/27/2024 KHUONG TRUONG
Plan Check Approved 4/29/2024 KHUONG TRUONG
Issued 5/20/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/19/2023 JILVER MAZARIEGOS
Eng Process Fee Ord 176,300 Cleared 1/22/2024 KHAING AYE
Sewer availability Cleared 2/21/2024 KHAING AYE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/27/2024 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 7/2/2024 Approved JAMES CHAVEZ
Special/Order Compliance 7/2/2024 Corrections Issued JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 7/10/2024 Partial Approval JAMES CHAVEZ
PLUMBING-Rough 7/10/2024 Partial Approval JAMES CHAVEZ
BUILDING-Rough-Frame 7/24/2024 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Rough 7/24/2024 Approved JAMES CHAVEZ
Green Building Rough 7/24/2024 Not Ready for Inspection JAMES CHAVEZ
MERV13>=Rough 7/24/2024 Not Ready for Inspection JAMES CHAVEZ
BUILDING-Rough-Frame 8/6/2024 Partial Approval JOSEPH MCGARRY
MERV13>=Rough 8/6/2024 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 8/6/2024 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 8/9/2024 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 8/20/2024 Approved JOSEPH MCGARRY
Green Building Rough 8/20/2024 Approved JOSEPH MCGARRY
Insulation 8/20/2024 Approved JOSEPH MCGARRY
MERV13>=Rough 8/20/2024 Approved JOSEPH MCGARRY
Drywall Nailing 8/26/2024 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 8/26/2024 Approved JOSEPH MCGARRY
Shower Pan 8/26/2024 Approved JOSEPH MCGARRY
Final 10/11/2024 Corrections Issued BEN MOLSTAD
Green Building Final 10/11/2024 Corrections Issued BEN MOLSTAD
MERV13>=Final 10/11/2024 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 10/11/2024 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 10/11/2024 Approved BEN MOLSTAD
ELECTRICAL-Final 10/16/2024 Approved BEN MOLSTAD
Final 10/16/2024 Corrections Issued BEN MOLSTAD
Green Building Final 10/16/2024 Approved BEN MOLSTAD
HVAC-Final 10/16/2024 Approved BEN MOLSTAD
PLUMBING-Final 10/16/2024 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 10/16/2024 SGSOV Approved BEN MOLSTAD