500 W 148TH ST 90248
Certificate Information: 500 W 148TH ST 90248
- Application / Permit
- 23014-10000-03686
- Plan Check / Job No.
- B23LA17008
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan PROP. ONE STORY ADDITION: (240 SQ. FT.) TO (E) SFD AND REMODEL
- Permit Issued
- Issued on 5/20/2024
- Issuing Office
- Current Status
- Issued on 5/20/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2023 | KHUONG TRUONG |
| Corrections Issued | 11/2/2023 | KHUONG TRUONG |
| Plan Check Approved | 3/27/2024 | KHUONG TRUONG |
| Plan Check Approved | 4/29/2024 | KHUONG TRUONG |
| Issued | 5/20/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/19/2023 | JILVER MAZARIEGOS |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2024 | KHAING AYE |
| Sewer availability | Cleared | 2/21/2024 | KHAING AYE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/27/2024 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 7/2/2024 | Approved | JAMES CHAVEZ |
| Special/Order Compliance | 7/2/2024 | Corrections Issued | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2024 | Partial Approval | JAMES CHAVEZ |
| PLUMBING-Rough | 7/10/2024 | Partial Approval | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 7/24/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 7/24/2024 | Approved | JAMES CHAVEZ |
| Green Building Rough | 7/24/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| MERV13>=Rough | 7/24/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 8/6/2024 | Partial Approval | JOSEPH MCGARRY |
| MERV13>=Rough | 8/6/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/6/2024 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/9/2024 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/20/2024 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 8/20/2024 | Approved | JOSEPH MCGARRY |
| Insulation | 8/20/2024 | Approved | JOSEPH MCGARRY |
| MERV13>=Rough | 8/20/2024 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 8/26/2024 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/26/2024 | Approved | JOSEPH MCGARRY |
| Shower Pan | 8/26/2024 | Approved | JOSEPH MCGARRY |
| Final | 10/11/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 10/11/2024 | Corrections Issued | BEN MOLSTAD |
| MERV13>=Final | 10/11/2024 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 10/11/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 10/11/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 10/16/2024 | Approved | BEN MOLSTAD |
| Final | 10/16/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 10/16/2024 | Approved | BEN MOLSTAD |
| HVAC-Final | 10/16/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 10/16/2024 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 10/16/2024 | SGSOV Approved | BEN MOLSTAD |