1727 S ORANGE GROVE AVE 90019
Certificate Information: 1727 S ORANGE GROVE AVE 90019
- Application / Permit
- 23014-10000-03671
- Plan Check / Job No.
- B23LA16974
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan: One-Story Addition and Interior Remodel to an Existing One-Story SFD
- Permit Issued
- Issued on 12/13/2023
- Issuing Office
- Current Status
- Issued on 12/13/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2023 | DAVID CASTILLO |
| Corrections Issued | 9/16/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 11/13/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 11/16/2023 | DAVID CASTILLO |
| Plan Check Approved | 12/13/2023 | CAROLEAN BASMA |
| Issued | 12/13/2023 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 10/24/2023 | MITESH PATEL |
| Sewer availability | Cleared | 10/26/2023 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2023 | ARNULFO CHAMU |
| Roof/Waste drainage to street | Cleared | 11/7/2023 | ARNULFO CHAMU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/22/2023 | Approved | RICHARD DOCKUS |
| METHANE-Barrier | 12/22/2023 | Approved | RICHARD DOCKUS |
| METHANE-Subgrade | 12/22/2023 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 1/12/2024 | Partial Approval | RONNIE MINDANAO |
| Insulation | 1/17/2024 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2024 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 3/12/2024 | Approved | STUART CHAPMAN |
| HVAC-Rough | 3/12/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 3/12/2024 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 3/14/2024 | Partial Approval | STUART CHAPMAN |
| Insulation | 4/1/2024 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 4/1/2024 | Approved | STUART CHAPMAN |
| Shower Pan | 4/1/2024 | Approved | STUART CHAPMAN |
| Drywall Nailing | 4/5/2024 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 6/27/2024 | Approved | RICHARD DOCKUS |
| Final | 6/27/2024 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 6/27/2024 | Approved | RICHARD DOCKUS |
| Green Building Rough | 6/27/2024 | Approved | RICHARD DOCKUS |
| METHANE-Final | 6/27/2024 | Approved | RICHARD DOCKUS |
| METHANE-Rough | 6/27/2024 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 6/27/2024 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 6/27/2024 | Corrections Issued | RICHARD DOCKUS |
| Final | 7/15/2024 | Partial Approval | ARTHUR NEGRETE |
| Smoke Detectors | 7/15/2024 | Approved | ARTHUR NEGRETE |
| Final | 8/21/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Final | 8/22/2024 | Approved | ARTHUR NEGRETE |
| Final | 8/22/2024 | Partial Inspection | ARTHUR NEGRETE |
| HVAC-Final | 8/22/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 8/22/2024 | Approved | ARTHUR NEGRETE |