9222-9224 W MONTE MAR DR 90035

Certificate Information: 9222-9224 W MONTE MAR DR 90035

Application / Permit
23014-10000-03670
Plan Check / Job No.
B23LA16973
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION TWO STORIES, WITH ATTACHED TWO CAR GARAGE AND SECOND FLOOR ATTACHED ADU PER ORDINANCE
Permit Issued
Issued on 4/16/2024
Issuing Office
Current Status
CofO Issued on 5/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 CARLOS MONTES
Corrections Issued 9/18/2023 CARLOS MONTES
Quality Review Completed 9/20/2023 KEN GILL
Building Plans Picked Up 9/22/2023 APPLICANT
Applicant returned to address corrections 3/8/2024 CARLOS MONTES
Plan Check Approved 4/1/2024 CARLOS MONTES
No Progress 4/12/2024 CARLOS MONTES
Plan Check Approved 4/12/2024 CARLOS MONTES
Issued 4/16/2024 APPLICANT
Permit Finaled 5/14/2026 RICHARD STEINBACH
CofO Issued 5/14/2026 RICHARD STEINBACH
Permit Finaled 5/14/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 9/29/2023 ANTHONY MAINEZ
Permit Cleared 9/29/2023 ANTHONY MAINEZ
Trees in Parkway Cleared 12/14/2023 ADALBERTO VERA
Eng Process Fee Ord 176,300 Cleared 12/20/2023 ANTHONY MAINEZ
Low Impact Development (LID) Cleared 12/20/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 12/20/2023 DARIN LAM
Sewer availability Cleared 12/20/2023 ANTHONY MAINEZ
GPI Written Notices Cleared 4/1/2024 CARLOS MONTES
Grading Pre-Inspection Cleared 4/1/2024 CARLOS MONTES

Contact Information

Architect Leishman,, Thomas Edward; Lic. No.: C15059 28100 RIDGEFERN COURT      RANCHO PALOS VERDES, CA 90275
Contractor Owner-Builder       ,
Engineer Golabtounkar,, Tony Hamid; Lic. No.: C49104 1434 WESTWOOD BLVD ST 17      LOS ANGELES, CA 90024

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/10/2024 Not Ready for Inspection ASHLEY THOMPSON
Sewer 6/10/2024 Not Ready for Inspection ASHLEY THOMPSON
Underground Mechanical 7/3/2024 Partial Approval MEL KHACHATOURIAN
Deputy Drilled-In Anchors 7/23/2024 Conditional Approval ASHLEY THOMPSON
Deputy Reinf. Concrete 7/23/2024 Conditional Approval ASHLEY THOMPSON
Footing/Foundation/Slab 7/25/2024 Partial Approval STEPHANIE SWANSON
Grounding or Bonding 7/25/2024 Partial Approval STEPHANIE SWANSON
METHANE-Barrier 7/25/2024 Not Ready for Inspection STEPHANIE SWANSON
METHANE-Subgrade 7/25/2024 Partial Approval STEPHANIE SWANSON
Deputy Reinf. Concrete 8/2/2024 Conditional Approval ASHLEY THOMPSON
Footing/Foundation/Slab 8/8/2024 Partial Approval MEL KHACHATOURIAN
METHANE-Barrier 8/8/2024 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Subgrade 8/8/2024 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Subgrade 8/12/2024 Approved ASHLEY THOMPSON
Special/Order Compliance 8/12/2024 Partial Inspection REGINA MENDEZ
Deputy Methane Barrier 8/20/2024 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 8/20/2024 Approved ASHLEY THOMPSON
METHANE-Barrier 8/20/2024 Approved ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 9/17/2024 Partial Approval ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Approved SEAN HAUPT
PLUMBING-Rough 11/18/2024 Approved ARAM AVEDISIAN
Insulation 12/31/2024 Partial Approval EVAN COOPER
HVAC-Rough 1/13/2025 Approved SEAN HAUPT
BUILDING-Rough-Frame 2/21/2025 No Access for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 2/21/2025 No Access for Inspection MEL KHACHATOURIAN
Green Building Rough 2/21/2025 No Access for Inspection MEL KHACHATOURIAN
Interior/Exterior Lathing 2/21/2025 No Access for Inspection MEL KHACHATOURIAN
METHANE-Rough 2/21/2025 No Access for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 2/25/2025 Corrections Issued ARAM AVEDISIAN
METHANE-Rough 2/25/2025 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 2/25/2025 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 3/14/2025 Conditional Approval ARAM AVEDISIAN
ELECTRICAL-Rough 3/14/2025 Conditional Approval ARAM AVEDISIAN
Green Building Rough 3/14/2025 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 3/14/2025 Conditional Approval ARAM AVEDISIAN
Deputy Methane Barrier 3/17/2025 Approved DAVID FEILER
Insulation 3/25/2025 Approved ARAM AVEDISIAN
Drywall Nailing 5/8/2025 Conditional Approval ARAM AVEDISIAN
Interior/Exterior Lathing 5/8/2025 Partial Approval ARAM AVEDISIAN
Shower Pan 5/8/2025 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 5/9/2025 Conditional Approval ARAM AVEDISIAN
Gas Test 11/20/2025 Approved ASHLEY THOMPSON
ELECTRICAL-Final 3/26/2026 Approved WILBER ROSALES
PLUMBING-Final 3/26/2026 Approved WILBER ROSALES
HVAC-Final 4/7/2026 Approved EVAN COOPER
BUILDING-Rough-Frame 4/15/2026 Approved ASHLEY THOMPSON
Final 4/15/2026 Corrections Issued ASHLEY THOMPSON
Green Building Final 4/15/2026 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 4/15/2026 SGSOV Approved ASHLEY THOMPSON
Smoke Detectors 4/15/2026 Not Ready for Inspection ASHLEY THOMPSON
Final 5/1/2026 Conditional Approval WILBER ROSALES
Smoke Detectors 5/1/2026 Approved WILBER ROSALES
Service/Power Release 5/13/2026 Approved DAVID FEILER