420 W 110TH ST 90061
Certificate Information: 420 W 110TH ST 90061
- Application / Permit
- 23014-10000-03667
- Plan Check / Job No.
- B23LA16966
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: ADDITION OF 10'-0" x 10'-4" TO CREATE NEW BEDROOM TO (E) S.F.D PER ENGINEERING
- Permit Issued
- Issued on 1/11/2024
- Issuing Office
- Current Status
- CofO Issued on 7/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2023 | ALFRED RAMIREZ |
| Corrections Issued | 9/14/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 12/7/2023 | ALFRED RAMIREZ |
| Issued | 1/11/2024 | APPLICANT |
| CofO in Progress | 11/19/2024 | BEN MOLSTAD |
| CofO in Progress | 11/20/2024 | BEN MOLSTAD |
| CofO in Progress | 7/19/2025 | MICHAEL PELHAM |
| Permit Finaled | 7/19/2025 | RICHARD STEINBACH |
| CofO Issued | 7/19/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/19/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/21/2023 | NEIL TUANO |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2023 | NEIL TUANO |
| Sewer availability | Cleared | 9/22/2023 | NEIL TUANO |
| Tenant Habitability Plan | Cleared | 10/16/2023 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Xi,, Wang; Lic. No.: NA85148 | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/8/2024 | Corrections Issued | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 2/14/2024 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2024 | Partial Approval | JAMES CHAVEZ |
| Footing/Foundation/Slab | 2/27/2024 | Approved | JAMES CHAVEZ |
| Insulation | 2/27/2024 | Partial Approval | JAMES CHAVEZ |
| ELECTRICAL-Rough | 3/8/2024 | Corrections Issued | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2024 | Partial Approval | JAMES CHAVEZ |
| Wood Frame | 3/8/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 3/11/2024 | Approved | JAMES CHAVEZ |
| Special/Order Compliance | 3/11/2024 | Corrections Issued | JAMES CHAVEZ |
| Interior/Exterior Lathing | 3/18/2024 | Approved | BEN MOLSTAD |
| Insulation | 3/21/2024 | Corrections Issued | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 3/27/2024 | Approved | EUGENE CASSIDY |
| Green Building Rough | 3/27/2024 | Approved | EUGENE CASSIDY |
| Insulation | 3/27/2024 | Approved | EUGENE CASSIDY |
| MERV13>=Rough | 3/27/2024 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 4/1/2024 | Approved | JAMES CHAVEZ |
| Green Building Rough | 4/1/2024 | Approved | JAMES CHAVEZ |
| Final | 10/11/2024 | Not Ready for Inspection | BARRY HACHE |
| Green Building Final | 10/11/2024 | Approved | BARRY HACHE |
| MERV13>=Final | 10/11/2024 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 10/11/2024 | SGSOV Approved | BARRY HACHE |
| Smoke Detectors | 10/11/2024 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 11/19/2024 | Approved | BEN MOLSTAD |
| Final | 11/19/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 11/19/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 11/19/2024 | Approved | BEN MOLSTAD |
| Final | 11/20/2024 | Corrections Issued | BEN MOLSTAD |
| Final | 7/19/2025 | OK to Issue CofO | MICHAEL PELHAM |