1158 S LUCERNE BLVD 90019

Certificate Information: 1158 S LUCERNE BLVD 90019

Application / Permit
23014-10000-03643
Plan Check / Job No.
B23LA16868
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE WITH ADDITION TO A NEW DETACHED ADU PER LAMC 12.22 A.33 (c)-(d) (1-STORY) COMPLY WITH DEPARTMENT ORDER effective date 03/15/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 10/9/2024
Issuing Office
Current Status
CofO Issued on 10/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2023 APPLICANT
Assigned to Plan Check Engineer 9/21/2023 CARLOS MONTES
Corrections Issued 9/26/2023 CARLOS MONTES
Quality Review Completed 9/28/2023 GARO TELMI
Applicant returned to address corrections 10/25/2023 CARLOS MONTES
Plan Check Approved 9/3/2024 CARLOS MONTES
Issued 10/9/2024 APPLICANT
CofO in Progress 8/22/2025 WILLIAM MICHALAK
Permit Finaled 10/16/2025 CLAUDIO MORENO
CofO Issued 10/16/2025 CLAUDIO MORENO
Permit Finaled 10/16/2025 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 10/6/2023 JEANIE LAM
Roof/Waste drainage to street Cleared 10/6/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/12/2023 JEANIE LAM
Sewer availability Cleared 10/12/2023 JEANIE LAM
Flood clearance Cleared 8/23/2024 RAYMOND LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: NA4808       ,

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/24/2024 Corrections Issued WILLIAM MICHALAK
FLOOD-Elevation Certificate 10/24/2024 Not Ready for Inspection WILLIAM MICHALAK
Footing/Foundation/Slab 10/24/2024 Corrections Issued WILLIAM MICHALAK
METHANE-Barrier 10/24/2024 Approved WILLIAM MICHALAK
METHANE-Subgrade 10/24/2024 Approved WILLIAM MICHALAK
Excavation/Setback/Form/Re-Bar 10/25/2024 Not Ready for Inspection WILLIAM MICHALAK
Excavation/Setback/Form/Re-Bar 11/8/2024 Partial Approval WILLIAM MICHALAK
FLOOD-Elevation Certificate 11/8/2024 Partial Approval WILLIAM MICHALAK
Footing/Foundation/Slab 11/8/2024 Not Ready for Inspection WILLIAM MICHALAK
Deputy Drilled-In Anchors 11/12/2024 Approved WILLIAM MICHALAK
Excavation/Setback/Form/Re-Bar 11/13/2024 Corrections Issued WILLIAM MICHALAK
Sewer 12/13/2024 Approved WILLIAM MICHALAK
Wood Frame 12/18/2024 Not Ready for Inspection WILLIAM MICHALAK
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Partial Approval WILLIAM MICHALAK
PLUMBING-Rough 12/24/2024 Approved WILLIAM MICHALAK
Wood Frame 1/6/2025 Partial Approval WILLIAM MICHALAK
BUILDING-Rough-Frame 1/17/2025 Not Ready for Inspection WILLIAM MICHALAK
FLOOD-Proofing Certificate 1/17/2025 Partial Approval WILLIAM MICHALAK
Green Building Rough 1/17/2025 Not Ready for Inspection WILLIAM MICHALAK
METHANE-Rough 1/17/2025 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 1/23/2025 Partial Approval LUIS CORRAL
FLOOD-Proofing Certificate 1/23/2025 Not Ready for Inspection LUIS CORRAL
Green Building Rough 1/23/2025 Not Ready for Inspection LUIS CORRAL
BUILDING-Rough-Frame 1/28/2025 Not Ready for Inspection LUIS CORRAL
FLOOD-Proofing Certificate 1/28/2025 Not Ready for Inspection LUIS CORRAL
Green Building Rough 1/28/2025 Partial Approval LUIS CORRAL
BUILDING-Rough-Frame 2/19/2025 Not Ready for Inspection WILLIAM MICHALAK
FLOOD-Proofing Certificate 2/19/2025 Partial Approval WILLIAM MICHALAK
Green Building Rough 2/19/2025 Not Ready for Inspection WILLIAM MICHALAK
BUILDING-Rough-Frame 2/26/2025 Not Ready for Inspection WILLIAM MICHALAK
FLOOD-Proofing Certificate 2/26/2025 Not Ready for Inspection WILLIAM MICHALAK
Green Building Rough 2/26/2025 Partial Approval WILLIAM MICHALAK
ELECTRICAL-Rough 4/17/2025 Approved WILLIAM MICHALAK
HVAC-Rough 4/17/2025 Approved WILLIAM MICHALAK
PLUMBING-Rough 4/17/2025 Approved WILLIAM MICHALAK
Insulation 5/1/2025 Corrections Issued WILLIAM MICHALAK
Interior/Exterior Lathing 5/1/2025 Corrections Issued WILLIAM MICHALAK
Drywall Nailing 5/6/2025 Approved LUIS CORRAL
Interior/Exterior Lathing 5/6/2025 Approved LUIS CORRAL
Interior/Exterior Lathing 5/27/2025 Approved WILLIAM MICHALAK
Deck 7/9/2025 Partial Approval WILLIAM MICHALAK
BUILDING-Rough-Frame 8/4/2025 Approved WILLIAM MICHALAK
FLOOD-Elevation Certificate 8/4/2025 Approved WILLIAM MICHALAK
FLOOD-Proofing Certificate 8/4/2025 Approved WILLIAM MICHALAK
Final 8/4/2025 Not Ready for Inspection WILLIAM MICHALAK
Footing/Foundation/Slab 8/4/2025 Approved WILLIAM MICHALAK
Green Building Final 8/4/2025 Approved WILLIAM MICHALAK
Green Building Rough 8/4/2025 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 8/4/2025 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 8/4/2025 Partial Approval WILLIAM MICHALAK
Final 8/22/2025 OK to Issue CofO WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 8/22/2025 SGSOV Approved WILLIAM MICHALAK
Service/Power Release 8/22/2025 Approved WILLIAM MICHALAK
Smoke Detectors 8/22/2025 Approved WILLIAM MICHALAK