635 W 109TH ST 90044
Certificate Information: 635 W 109TH ST 90044
- Application / Permit
- 23014-10000-03635
- Plan Check / Job No.
- B23LA16841
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN. Addition of laundry room and covered porch to the side of (E) SFD.
- Permit Issued
- Issued on 11/29/2023
- Issuing Office
- Current Status
- CofO Issued on 11/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2023 | AMY GUEVARRA |
| Corrections Issued | 10/5/2023 | AMY GUEVARRA |
| Applicant returned to address corrections | 10/27/2023 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 11/14/2023 | JOHNPAUL ISIP |
| Plan Check Approved | 11/28/2023 | JOHNPAUL ISIP |
| Issued | 11/29/2023 | APPLICANT |
| CofO in Progress | 10/22/2024 | BEN MOLSTAD |
| Permit Finaled | 11/5/2024 | ANSON MAGLASANG |
| CofO Issued | 11/5/2024 | ANSON MAGLASANG |
| Permit Finaled | 11/5/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2023 | ARNULFO CHAMU |
| Roof/Waste drainage to street | Cleared | 10/26/2023 | ARNULFO CHAMU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/18/2024 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2024 | Partial Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Partial Approval | JAMES CHAVEZ |
| Wood Frame | 2/15/2024 | Corrections Issued | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2024 | Partial Approval | JAMES CHAVEZ |
| Wood Frame | 3/7/2024 | Corrections Issued | JAMES CHAVEZ |
| Insulation | 3/13/2024 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 4/12/2024 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2024 | Partial Approval | JAMES CHAVEZ |
| Green Building Rough | 4/12/2024 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 4/23/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 7/10/2024 | Approved | JAMES CHAVEZ |
| Final | 7/10/2024 | Corrections Issued | JAMES CHAVEZ |
| Green Building Final | 7/10/2024 | Approved | JAMES CHAVEZ |
| Smoke Detectors | 7/10/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 7/18/2024 | Corrections Issued | JAMES CHAVEZ |
| Smoke Detectors | 7/18/2024 | Approved | JAMES CHAVEZ |
| Final | 10/22/2024 | OK to Issue CofO | BEN MOLSTAD |