2241 1/2 W CAMBRIDGE ST 90006
Certificate Information: 2241 1/2 W CAMBRIDGE ST 90006
- Application / Permit
- 23014-10000-03601
- Plan Check / Job No.
- B23LA16672
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing detached garage of 361 SF into accessory dwelling per CA Govt. Code 65852.2(e)(1)(A). All work per WFPP. **ePLAN**
- Permit Issued
- Issued on 11/2/2023
- Issuing Office
- Current Status
- CofO Issued on 2/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2023 | VICTOR CHEN |
| Corrections Issued | 9/14/2023 | VICTOR CHEN |
| Applicant returned to address corrections | 10/17/2023 | VICTOR CHEN |
| Plan Check Approved | 11/2/2023 | VICTOR CHEN |
| Issued | 11/2/2023 | APPLICANT |
| CofO in Progress | 2/21/2025 | WILLIAM SIERRA |
| Permit Finaled | 2/23/2025 | DEROLD HAUFF |
| CofO Issued | 2/23/2025 | DEROLD HAUFF |
| Permit Finaled | 2/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/25/2023 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 9/25/2023 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2023 | JESSICA OPINION |
| Sewer availability | Cleared | 9/28/2023 | JESSICA OPINION |
| City Hist. Cultural Monument | Cleared | 10/12/2023 | ERIK VAN BREENE |
| HPOZ | Cleared | 10/12/2023 | ERIK VAN BREENE |
| Historic monument | Cleared | 10/18/2023 | ERIK VAN BREENE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/13/2023 | Approved | KATHRYN BUTTERWORTH |
| Sewer | 11/13/2023 | Approved | KATHRYN BUTTERWORTH |
| Underground Mechanical | 11/13/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Underground Mechanical | 11/15/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Deputy Drilled-In Anchors | 11/21/2023 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 11/22/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 11/28/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 12/15/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 2/8/2024 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/15/2024 | Approved | ARTHUR NEGRETE |
| Pre-Inspection | 2/29/2024 | Approved | ARTHUR NEGRETE |
| Special/Order Compliance | 3/7/2024 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 3/14/2024 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 3/27/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 3/27/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 4/1/2024 | Approved | ARTHUR NEGRETE |
| Insulation | 4/3/2024 | Not Ready for Inspection | JOSH MEISTER |
| Shower Pan | 4/3/2024 | Approved | JOSH MEISTER |
| Insulation | 4/5/2024 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 4/12/2024 | Approved | ARTHUR NEGRETE |
| Final | 5/1/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 5/1/2024 | SGSOV Not Ready | ARTHUR NEGRETE |
| Smoke Detectors | 5/1/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Pre-Gunite | 5/6/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 5/9/2024 | Corrections Issued | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 5/9/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 5/9/2024 | Approved | ARTHUR NEGRETE |
| Final | 8/19/2024 | Corrections Issued | WILLIAM SIERRA |
| Final | 9/6/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| ELECTRICAL-Final | 10/18/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Final | 10/18/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Final | 10/18/2024 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Final | 10/24/2024 | Corrections Issued | WILLIAM SIERRA |
| HVAC-Final | 10/24/2024 | Corrections Issued | WILLIAM SIERRA |
| PLUMBING-Final | 10/24/2024 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Final | 11/25/2024 | Approved | WILLIAM SIERRA |
| Final | 11/25/2024 | Corrections Issued | WILLIAM SIERRA |
| Gas Test | 11/25/2024 | Approved | WILLIAM SIERRA |
| HVAC-Final | 11/25/2024 | Approved | WILLIAM SIERRA |
| Service/Power Release | 11/25/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| Final | 2/6/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Service/Power Release | 2/14/2025 | Approved | WILLIAM SIERRA |
| Special/Order Compliance | 2/14/2025 | Approved | WILLIAM SIERRA |
| Final | 2/20/2025 | OK to Issue CofO | WILLIAM SIERRA |