1495 S ROXBURY DR 90035

Certificate Information: 1495 S ROXBURY DR 90035

Application / Permit
23014-10000-03573
Plan Check / Job No.
B23LA16566
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL + 2-STORY ADDITION WITH ATTACHED 2-CAR GARAGE TO (E) SFD. NFPA 13D FIRE SPRINKLER SYSTEM IS REQUIRED.
Permit Issued
Issued on 3/1/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2023 APPLICANT
Assigned to Plan Check Engineer 9/7/2023 NGHI SU
Corrections Issued 9/9/2023 NGHI SU
Quality Review Completed 9/15/2023 KEN GILL
Building Plans Picked Up 9/15/2023 APPLICANT
Applicant returned to address corrections 1/23/2024 NGHI SU
Plan Check Approved 1/31/2024 NGHI SU
Issued 3/1/2024 APPLICANT
Permit Finaled 12/23/2025 RICHARD STEINBACH
CofO Issued 12/23/2025 RICHARD STEINBACH
Permit Finaled 12/23/2025 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development (LID) Cleared 12/6/2023 LUIS LUVANO
Eng Process Fee Ord 176,300 Cleared 12/12/2023 BRENDEN HAWK
Sewer availability Cleared 12/12/2023 BRENDEN HAWK
Roof/Waste drainage to street Cleared 12/19/2023 DARIN LAM
Specific Plan Cleared 12/22/2023 MOHAMMAD HASAN
Drainage to Storm Drain Cleared 1/17/2024 DARIN LAM
GPI Written Notices Cleared 1/29/2024 NGHI SU
Grading Pre-Inspection Cleared 1/29/2024 NGHI SU

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,
Engineer Nester,, Melvin Russell; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063
Engineer Winn,, Rebecca Michelle; Lic. No.: L7699 1238 OAK VIEW LN      LA VERNE, CA 91750

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/21/2024 Partial Approval MEL KHACHATOURIAN
METHANE-Barrier 5/21/2024 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Subgrade 5/21/2024 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Rough 6/4/2024 Partial Approval JESUS RODRIGUEZ
METHANE-Subgrade 6/4/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 6/4/2024 Partial Approval JESUS RODRIGUEZ
Deputy Drilled-In Anchors 6/28/2024 Conditional Approval ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 6/28/2024 Approved SEAN HAUPT
Footing/Foundation/Slab 6/28/2024 Approved SEAN HAUPT
METHANE-Barrier 6/28/2024 Approved SEAN HAUPT
Deputy Reinf. Concrete 7/1/2024 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 8/19/2024 Partial Approval ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 9/6/2024 Corrections Issued SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 9/9/2024 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 10/9/2024 Not Ready for Inspection ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Corrections Issued ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Partial Approval SEAN HAUPT
HVAC-Rough 10/22/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 11/1/2024 Corrections Issued ASHLEY THOMPSON
HVAC-Rough 11/4/2024 Partial Approval ASHLEY THOMPSON
PLUMBING-Rough 11/4/2024 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Rough 11/7/2024 No Access for Inspection ASHLEY THOMPSON
METHANE-Rough 11/12/2024 Approved ASHLEY THOMPSON
PLUMBING-Rough 11/12/2024 Partial Approval ASHLEY THOMPSON
ELECTRICAL-Rough 11/14/2024 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 11/14/2024 Partial Approval ASHLEY THOMPSON
ELECTRICAL-Rough 11/18/2024 Approved ARAM AVEDISIAN
Pre-Inspection 11/18/2024 Partial Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 11/21/2024 Corrections Issued ASHLEY THOMPSON
HVAC-Rough 11/21/2024 Corrections Issued ASHLEY THOMPSON
Deputy Wood Construction 12/26/2024 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 12/26/2024 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 12/26/2024 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 1/21/2025 Approved EVAN COOPER
Green Building Rough 1/21/2025 Approved EVAN COOPER
Interior/Exterior Lathing 1/21/2025 Partial Inspection EVAN COOPER
Verify Sprinkler Sign Off 1/21/2025 Approved EVAN COOPER
Wood Frame 1/21/2025 Approved EVAN COOPER
Insulation 2/7/2025 Approved ARAM AVEDISIAN
Drywall Nailing 2/18/2025 Approved REGINA MENDEZ
Shower Pan 2/18/2025 Not Ready for Inspection REGINA MENDEZ
Shower Pan 2/20/2025 Not Ready for Inspection JAYLIN GRAVITTE
Shower Pan 2/21/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 3/3/2025 Approved REGINA MENDEZ
Sewer 9/3/2025 Approved ASHLEY THOMPSON
Underground Mechanical 9/3/2025 Partial Approval ASHLEY THOMPSON
Underground Mechanical 9/8/2025 Approved ASHLEY THOMPSON
ELECTRICAL-Final 10/28/2025 Corrections Issued MEL KHACHATOURIAN
HVAC-Final 11/18/2025 Corrections Issued MEL KHACHATOURIAN
PLUMBING-Final 11/18/2025 Corrections Issued MEL KHACHATOURIAN
ELECTRICAL-Final 11/26/2025 Approved ASHLEY THOMPSON
Final 11/26/2025 Corrections Issued ASHLEY THOMPSON
Green Building Final 11/26/2025 Approved ASHLEY THOMPSON
HVAC-Final 11/26/2025 Corrections Issued ASHLEY THOMPSON
PLUMBING-Final 11/26/2025 Not Ready for Inspection ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 11/26/2025 SGSOV Approved ASHLEY THOMPSON
Smoke Detectors 11/26/2025 Approved ASHLEY THOMPSON
Final 12/18/2025 Conditional Approval ASHLEY THOMPSON
HVAC-Final 12/18/2025 Approved ASHLEY THOMPSON
PLUMBING-Final 12/18/2025 Approved ASHLEY THOMPSON
Service/Power Release 12/18/2025 Approved ASHLEY THOMPSON