11955 W SUNSET BLVD 90049

Certificate Information: 11955 W SUNSET BLVD 90049

Application / Permit
23014-10000-03571
Plan Check / Job No.
B23LA16559
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(18) Private School
Work Description
PROPOSED ADDITION OF COVERED PORCH AT THE ENTRY.
Permit Issued
Issued on 7/11/2024
Issuing Office
West Los Angeles
Current Status
Issued on 7/11/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/6/2023 APPLICANT
Assigned to Plan Check Engineer 9/7/2023 MICHAEL LOPEZ
Corrections Issued 9/28/2023 MICHAEL LOPEZ
Quality Review Completed 9/29/2023 KEN GILL
Building Plans Picked Up 10/5/2023 APPLICANT
Disabled Access Plans Picked Up 12/12/2023 APPLICANT
Plan Check Approved 3/28/2024 MICHAEL LOPEZ
Issued 7/11/2024 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 10/12/2023 MAYELA VILLA
ZA Case Cleared 10/12/2023 MAYELA VILLA
ZA Case Cleared 10/12/2023 MAYELA VILLA
ZA Case Cleared 10/12/2023 MAYELA VILLA
Eng Process Fee Ord 176,300 Cleared 10/27/2023 BRENDEN HAWK
Roof/Waste drainage to street Cleared 10/27/2023 BRENDEN HAWK
DAS Clearance Cleared 2/16/2024 MICHAEL LOPEZ
Grading Pre-Inspection Cleared 3/16/2024 VASIL MIHALEV

Contact Information

Architect Park,, Jay H.; Lic. No.: C36800 3850 WILSHIRE BLVD #308      LOS ANGELES, CA 90010
Contractor E P I Construction Inc; Lic. No.: 865616-B 12345 VENTURA BLVD SUITE H      STUDIO CITY, CA 91604
Engineer Hwang,, Junho; Lic. No.: S5592 815 FAIRVIEW AVE #205      SOUTH PASADENA, CA 91030

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/15/2024 Not Ready for Inspection CASIMIR BRITTON
Pre-Inspection 7/15/2024 Partial Inspection CASIMIR BRITTON
Deputy Reinf. Concrete 7/18/2024 Conditional Approval CASIMIR BRITTON
Wood Frame 7/24/2024 Not Ready for Inspection CASIMIR BRITTON
Deputy Reinf. Concrete 7/25/2024 Conditional Approval CASIMIR BRITTON
Light Gage Steel Frame 7/27/2024 Partial Inspection CASIMIR BRITTON
Drywall Nailing 7/29/2024 Partial Inspection CASIMIR BRITTON
Interior/Exterior Lathing 7/30/2024 Partial Inspection CASIMIR BRITTON
Final 8/9/2024 Partial Approval RICARDO ROBLES
Footing/Foundation/Slab 8/9/2024 Approved RICARDO ROBLES
Reinforced Masonry Frame 8/9/2024 Approved RICARDO ROBLES
Smoke Detectors 8/9/2024 Approved RICARDO ROBLES
Final 8/23/2024 Not Ready for Inspection CASIMIR BRITTON