3446 N WONDER VIEW SQ 90068

Certificate Information: 3446 N WONDER VIEW SQ 90068

Application / Permit
23014-10000-03565
Plan Check / Job No.
B23LA16527
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan New addition to (E) 1-story SFD over Basement, Convert Att. Caroport to Garage, with Interior & Exterior Str. Remodel
Permit Issued
Issued on 11/14/2023
Issuing Office
Current Status
CofO Issued on 4/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/5/2023 APPLICANT
Assigned to Plan Check Engineer 9/7/2023 MAHNAZ NOURHASHEMI
Corrections Issued 9/16/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 9/27/2023 TU HUA
Plan Check Approved 11/14/2023 MAHNAZ NOURHASHEMI
Issued 11/14/2023 APPLICANT
CofO in Progress 4/17/2025 BRIAN SULLIVAN
No Progress 4/20/2025 DEROLD HAUFF
CofO in Progress 4/20/2025 DEROLD HAUFF
Permit Finaled 4/23/2025 DEROLD HAUFF
CofO Issued 4/23/2025 DEROLD HAUFF
Permit Finaled 4/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/27/2023 JESSICA OPINION
Sewer availability Cleared 9/27/2023 JESSICA OPINION
Grading Pre-Inspection Cleared 10/17/2023 MAHNAZ NOURHASHEMI
Roof/Waste drainage to street Cleared 11/1/2023 ARNULFO CHAMU

Contact Information

Contractor Owner-Builder       ,
Engineer Nazarians,, Harmick; Lic. No.: C91232 9825 OSO AVE      CHATSWORTH, CA 91311

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/2/2024 Corrections Issued BRIAN SULLIVAN
Pre-Inspection 7/2/2024 Not Ready for Inspection BRIAN SULLIVAN
Deputy Drilled-In Anchors 7/3/2024 Conditional Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 7/5/2024 Partial Approval BRIAN SULLIVAN
Deputy Drilled-In Anchors 8/5/2024 Conditional Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 8/16/2024 Approved BRIAN SULLIVAN
Footing/Foundation/Slab 8/16/2024 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 8/19/2024 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 9/16/2024 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 10/1/2024 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 10/1/2024 Corrections Issued BRIAN SULLIVAN
HVAC-Rough 10/1/2024 Corrections Issued BRIAN SULLIVAN
Deputy Wood Construction 10/4/2024 Conditional Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 10/9/2024 Conditional Approval BRIAN SULLIVAN
ELECTRICAL-Rough 10/9/2024 Corrections Issued BRIAN SULLIVAN
HVAC-Rough 10/9/2024 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 10/29/2024 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 10/29/2024 Approved BRIAN SULLIVAN
Insulation 10/29/2024 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 10/29/2024 Approved BRIAN SULLIVAN
Drywall Nailing 11/13/2024 Approved BRIAN SULLIVAN
Final 3/18/2025 Corrections Issued BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 3/18/2025 SGSOV Not Ready BRIAN SULLIVAN
Smoke Detectors 3/18/2025 Partial Inspection BRIAN SULLIVAN
Final 4/16/2025 OK to Issue CofO BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 4/16/2025 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 4/16/2025 Approved BRIAN SULLIVAN