1743 W 83RD ST 90047

Certificate Information: 1743 W 83RD ST 90047

Application / Permit
23014-10000-03560
Plan Check / Job No.
B23LA16495
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
DEMO (E) PATIO COVER AND REPLACE WITH ENCLOSED PORCH IN FRONT OF (E) SFD.
Permit Issued
Issued on 12/18/2023
Issuing Office
Current Status
Issued on 12/18/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/5/2023 APPLICANT
Assigned to Plan Check Engineer 9/5/2023 JOSEPH RAFOLS
Corrections Issued 9/5/2023 JOSEPH RAFOLS
Applicant returned to address corrections 12/6/2023 WEIJIAN HUANG
Applicant returned to address corrections 12/12/2023 CRISTINA SALAZAR
Plan Check Approved 12/15/2023 JOSEPH RAFOLS
Issued 12/18/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/15/2023 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 12/6/2023 DAVID LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/24/2024 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Corrections Issued JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Partial Inspection JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 3/13/2024 Partial Approval JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 3/26/2024 Approved JOSE MACIAS
Drywall Nailing 4/8/2024 Not Ready for Inspection JOSE MACIAS
Interior/Exterior Lathing 4/8/2024 Approved JOSE MACIAS
Wood Frame 4/8/2024 Approved JOSE MACIAS
ELECTRICAL-Rough 4/19/2024 Not Ready for Inspection JOSE MACIAS
Insulation 4/19/2024 Corrections Issued JOSE MACIAS
Insulation 4/26/2024 Approved JOSH MEISTER
Drywall Nailing 5/8/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 9/17/2024 Approved AMIR NAZARIAN
Final 9/17/2024 Corrections Issued AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 9/17/2024 SGSOV Not Ready AMIR NAZARIAN
Smoke Detectors 9/17/2024 Approved AMIR NAZARIAN
Final 10/2/2024 Conditional Approval AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 10/2/2024 SGSOV Approved AMIR NAZARIAN