920 1/2 N BROAD AVE 90744
Certificate Information: 920 1/2 N BROAD AVE 90744
- Application / Permit
- 23014-10000-03547
- Plan Check / Job No.
- B23LA16441
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT (E) DETACHED GARAGE 326SQFT WITH NEW ADDITION 498SQDT INTO AN ACCESSORY DWELLING UNIT 824SQFT PER LAMC 12.22 A.33(c)-(d)
- Permit Issued
- Issued on 5/6/2024
- Issuing Office
- Current Status
- CofO Issued on 1/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2023 | KEVIN MORALES |
| Corrections Issued | 9/14/2023 | KEVIN MORALES |
| Applicant returned to address corrections | 2/16/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 3/9/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 4/8/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 4/11/2024 | KHUONG TRUONG |
| Issued | 5/6/2024 | APPLICANT |
| CofO in Progress | 1/5/2026 | JOSEPH MCGARRY |
| Permit Finaled | 1/5/2026 | ANSON MAGLASANG |
| CofO Issued | 1/5/2026 | ANSON MAGLASANG |
| Permit Finaled | 1/5/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 12/12/2023 | JILVER MAZARIEGOS |
| Roof/Waste drainage to street | Cleared | 12/12/2023 | JILVER MAZARIEGOS |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2024 | JILVER MAZARIEGOS |
| Sewer availability | Cleared | 2/27/2024 | JILVER MAZARIEGOS |
| "Q" conditions | Cleared | 3/1/2024 | RYAN LY |
| Clean Up Green Up | Cleared | 3/1/2024 | RYAN LY |
| Low Impact Development (LID) | Cleared | 3/5/2024 | MELINEH AGHAKHABIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/9/2025 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 5/9/2025 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 5/9/2025 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 5/9/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 5/9/2025 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/26/2025 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 6/26/2025 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2025 | Partial Approval | EUGENE CASSIDY |
| Gas Test | 6/26/2025 | Approved | EUGENE CASSIDY |
| Green Building Rough | 6/26/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 6/26/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 6/26/2025 | Corrections Issued | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 6/27/2025 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Approved | JOHN KLARIN |
| Gas Test | 7/2/2025 | Approved | JOHN KLARIN |
| Insulation | 7/2/2025 | Approved | JOHN KLARIN |
| Drywall Nailing | 7/10/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/10/2025 | Approved | EUGENE CASSIDY |
| Gas Test | 8/14/2025 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/31/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/31/2025 | Approved | EUGENE CASSIDY |
| Final | 10/31/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 10/31/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 10/31/2025 | Approved | EUGENE CASSIDY |
| HVAC-Final | 10/31/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 10/31/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/31/2025 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 10/31/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 10/31/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/24/2025 | Approved | EUGENE CASSIDY |
| Final | 12/24/2025 | Corrections Issued | EUGENE CASSIDY |
| Gas Test | 12/24/2025 | Approved | EUGENE CASSIDY |
| Green Building Final | 12/24/2025 | Approved | EUGENE CASSIDY |
| HVAC-Final | 12/24/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 12/24/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 12/24/2025 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 12/24/2025 | Not Required | EUGENE CASSIDY |
| Final | 12/31/2025 | OK to Issue CofO | JOSEPH MCGARRY |