12719 W GILMORE AVE 90066

Certificate Information: 12719 W GILMORE AVE 90066

Application / Permit
23014-10000-03540
Plan Check / Job No.
B23LA16011
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER LAMC 12.22 A.33 (c)-(d) (2-STORY)
Permit Issued
Issued on 4/8/2025
Issuing Office
Current Status
Issued on 4/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/25/2023 APPLICANT
Assigned to Plan Check Engineer 8/31/2023 JOSEPH RAFOLS
Corrections Issued 9/5/2023 CARLOS MONTES
Quality Review Completed 9/6/2023 GARO TELMI
Applicant returned to address corrections 12/11/2024 CARLOS MONTES
Applicant returned to address corrections 1/28/2025 CARLOS MONTES
Applicant returned to address corrections 2/28/2025 CARLOS MONTES
Applicant returned to address corrections 3/27/2025 CARLOS MONTES
Plan Check Approved 4/1/2025 JOSEPH RAFOLS
Issued 4/8/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/25/2023 KIMBERLY HERNANDEZ
Specific Plan Cleared 10/18/2023 FREDDY GARCIA
Eng Process Fee Ord 176,300 Cleared 12/21/2023 KIMBERLY HERNANDEZ
Sewer availability Cleared 12/21/2023 KIMBERLY HERNANDEZ
Low Impact Development (LID) Cleared 5/2/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 5/8/2024 KIMBERLY HERNANDEZ

Contact Information

Contractor S M Development Company Inc; Lic. No.: 450270-B       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: NA67449       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/22/2025 Approved RUBEN RIVAS
Footing/Foundation/Slab 7/22/2025 Approved RUBEN RIVAS
Grounding or Bonding 7/22/2025 Approved RUBEN RIVAS
Sewer 7/22/2025 Approved RUBEN RIVAS
Underground Mechanical 7/22/2025 Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 8/14/2025 Partial Approval MICHAEL ALLEN
PLUMBING-Rough 8/28/2025 Approved RUBEN RIVAS
ELECTRICAL-Rough 10/27/2025 Corrections Issued RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 10/27/2025 Approved RUBEN RIVAS
Green Building Rough 10/27/2025 Approved RUBEN RIVAS
HVAC-Rough 10/27/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 10/27/2025 Partial Approval RUBEN RIVAS
Verify Sprinkler Sign Off 10/27/2025 Approved RUBEN RIVAS
ELECTRICAL-Rough 12/11/2025 Approved ANTHONY EGSON
Insulation 12/11/2025 Approved ANTHONY EGSON
Wood Frame 12/11/2025 Approved ANTHONY EGSON
Drywall Nailing 12/15/2025 Not Ready for Inspection ANTHONY EGSON
Drywall Nailing 12/16/2025 Partial Approval MICHAEL ALLEN
Shower Pan 12/16/2025 Approved MICHAEL ALLEN
Special/Order Compliance 12/16/2025 Corrections Issued MICHAEL ALLEN