2528 S 8TH AVE 90018
Certificate Information: 2528 S 8TH AVE 90018
- Application / Permit
- 23014-10000-03537
- Plan Check / Job No.
- B23LA16413
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Alteration to (E) 2-Story SFD to convert porch to be part of SFD
- Permit Issued
- Issued on 5/8/2024
- Issuing Office
- Current Status
- CofO Issued on 1/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2023 | GEORGE JOLAKIAN |
| Corrections Issued | 9/21/2023 | GEORGE JOLAKIAN |
| Quality Review Completed | 9/28/2023 | RODOLFO ARIAS |
| Plan Check Approved | 5/7/2024 | GEORGE JOLAKIAN |
| Issued | 5/8/2024 | APPLICANT |
| CofO in Progress | 1/16/2025 | JUSTIN HAWLEY |
| Permit Finaled | 1/26/2025 | DEROLD HAUFF |
| CofO Issued | 1/26/2025 | DEROLD HAUFF |
| Permit Finaled | 1/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2023 | DAVID VO |
| Roof/Waste drainage to street | Cleared | 11/15/2023 | DAVID VO |
| Sewer availability | Cleared | 11/15/2023 | DAVID VO |
| CPC | Cleared | 4/10/2024 | DEBORAH MCGILL |
| HPOZ | Cleared | 4/10/2024 | DEBORAH MCGILL |
| ZA Case | Cleared | 4/10/2024 | DEBORAH MCGILL |
| ZI | Cleared | 4/10/2024 | DEBORAH MCGILL |
Contact Information
| Contractor | Manuel Oquendo; Lic. No.: 1049589-B | , |
| Engineer | Karapetian,, Arbi; Lic. No.: C79953 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
| Engineer | Karapetian,, Arbi; Lic. No.: NA79953 | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Partial Approval | JUSTIN HAWLEY |
| Green Building Rough | 10/17/2024 | Approved | JUSTIN HAWLEY |
| MERV13>=Rough | 10/17/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 10/28/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 10/28/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 10/28/2024 | Approved | JOSE MACIAS |
| Deputy Wood Construction | 10/31/2024 | Conditional Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 11/5/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 11/5/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 11/5/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 11/5/2024 | Partial Approval | JUSTIN HAWLEY |
| Shower Pan | 11/5/2024 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 11/12/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 11/12/2024 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 1/16/2025 | Approved | JUSTIN HAWLEY |
| Final | 1/16/2025 | OK to Issue CofO | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 1/16/2025 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 1/16/2025 | Approved | JUSTIN HAWLEY |
| MERV13>=Final | 1/16/2025 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 1/16/2025 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 1/16/2025 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 1/16/2025 | Approved | JUSTIN HAWLEY |