2528 S 8TH AVE 90018

Certificate Information: 2528 S 8TH AVE 90018

Application / Permit
23014-10000-03537
Plan Check / Job No.
B23LA16413
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Alteration to (E) 2-Story SFD to convert porch to be part of SFD
Permit Issued
Issued on 5/8/2024
Issuing Office
Current Status
CofO Issued on 1/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 GEORGE JOLAKIAN
Corrections Issued 9/21/2023 GEORGE JOLAKIAN
Quality Review Completed 9/28/2023 RODOLFO ARIAS
Plan Check Approved 5/7/2024 GEORGE JOLAKIAN
Issued 5/8/2024 APPLICANT
CofO in Progress 1/16/2025 JUSTIN HAWLEY
Permit Finaled 1/26/2025 DEROLD HAUFF
CofO Issued 1/26/2025 DEROLD HAUFF
Permit Finaled 1/26/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/15/2023 DAVID VO
Roof/Waste drainage to street Cleared 11/15/2023 DAVID VO
Sewer availability Cleared 11/15/2023 DAVID VO
CPC Cleared 4/10/2024 DEBORAH MCGILL
HPOZ Cleared 4/10/2024 DEBORAH MCGILL
ZA Case Cleared 4/10/2024 DEBORAH MCGILL
ZI Cleared 4/10/2024 DEBORAH MCGILL

Contact Information

Contractor Manuel Oquendo; Lic. No.: 1049589-B       ,
Engineer Karapetian,, Arbi; Lic. No.: C79953 6854 FOOTHILL BLVD      TUJUNGA, CA 91042
Engineer Karapetian,, Arbi; Lic. No.: NA79953       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 10/17/2024 Partial Approval JUSTIN HAWLEY
Green Building Rough 10/17/2024 Approved JUSTIN HAWLEY
MERV13>=Rough 10/17/2024 Approved JUSTIN HAWLEY
ELECTRICAL-Rough 10/28/2024 Approved JOSE MACIAS
HVAC-Rough 10/28/2024 Approved JOSE MACIAS
PLUMBING-Rough 10/28/2024 Approved JOSE MACIAS
Deputy Wood Construction 10/31/2024 Conditional Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 11/5/2024 Approved JUSTIN HAWLEY
Green Building Rough 11/5/2024 Approved JUSTIN HAWLEY
Insulation 11/5/2024 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 11/5/2024 Partial Approval JUSTIN HAWLEY
Shower Pan 11/5/2024 Approved JUSTIN HAWLEY
Drywall Nailing 11/12/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 11/12/2024 Approved JOSH MEISTER
ELECTRICAL-Final 1/16/2025 Approved JUSTIN HAWLEY
Final 1/16/2025 OK to Issue CofO JUSTIN HAWLEY
Footing/Foundation/Slab 1/16/2025 Approved JUSTIN HAWLEY
HVAC-Final 1/16/2025 Approved JUSTIN HAWLEY
MERV13>=Final 1/16/2025 Approved JUSTIN HAWLEY
PLUMBING-Final 1/16/2025 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 1/16/2025 SGSOV Approved JUSTIN HAWLEY
Smoke Detectors 1/16/2025 Approved JUSTIN HAWLEY