16074 W ROYAL OAK ROAD 91436

Certificate Information: 16074 W ROYAL OAK ROAD 91436

Application / Permit
23014-10000-03518
Plan Check / Job No.
B23LA16346
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan ADDITION AND INTERIOR REMODEL TO (E) 2-STORY SFD.
Permit Issued
Issued on 9/5/2025
Issuing Office
Current Status
Issued on 9/5/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/7/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 ADRIANA LOPEZ
Corrections Issued 9/20/2023 ADRIANA LOPEZ
Quality Review Completed 9/22/2023 GARO TELMI
Plan Check Approved 12/19/2023 ADRIANA LOPEZ
No Progress 6/3/2025 ADRIANA LOPEZ
Plan Check Approved 8/14/2025 ADRIANA LOPEZ
Issued 9/5/2025 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/3/2023 NIKKI ZULUETA
BHO/Hillside ordinance Cleared 10/3/2023 NIKKI ZULUETA
BHO/Hillside ordinance Cleared 10/3/2023 NIKKI ZULUETA
BHO/Hillside ordinance Cleared 10/3/2023 NIKKI ZULUETA
BHO/Hillside ordinance Cleared 10/3/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 10/3/2023 NIKKI ZULUETA
Roof/Waste drainage to street Cleared 10/3/2023 NIKKI ZULUETA

Contact Information

Architect Silberstein,, Matthew Lawrence; Lic. No.: C33687 209 LUXAIRE CT.      LAS VEGAS, NV 89144
Contractor Owner-Builder       ,
Engineer Ibarra,, Marco A; Lic. No.: C74010 2596 MISSION ST STE 330A      SAN MARINO, CA 91108

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Interior/Exterior Lathing 7/28/2026   

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 3/19/2026 Partial Approval THOMAS FINNILA
Deputy Steel/Welding 3/31/2026 Partial Approval SEAN WIRCH
ELECTRICAL-Rough 4/29/2026 Partial Approval THOMAS FINNILA
Insulation 5/6/2026 Partial Approval THOMAS FINNILA
Drywall Nailing 5/11/2026 Partial Approval THOMAS FINNILA
Green Building Rough 5/11/2026 Partial Approval THOMAS FINNILA
PLUMBING-Rough 5/13/2026 Approved THOMAS FINNILA
ELECTRICAL-Rough 5/27/2026 Approved SEAN WIRCH
BUILDING-Rough-Frame 5/28/2026 Approved THOMAS FINNILA
Green Building Rough 5/28/2026 Approved THOMAS FINNILA
HVAC-Rough 5/28/2026 Approved THOMAS FINNILA
Insulation 6/2/2026 Approved JUAN ALVARADO
Drywall Nailing 6/5/2026 Approved THOMAS FINNILA
Interior/Exterior Lathing 6/26/2026 Not Ready for Inspection JUAN ALVARADO
Shower Pan 7/2/2026 Corrections Issued SEAN WIRCH
Interior/Exterior Lathing 7/15/2026 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 7/22/2026 Corrections Issued THOMAS FINNILA