3554 1/2 E SISKIYOU ST 90023
Certificate Information: 3554 1/2 E SISKIYOU ST 90023
- Application / Permit
- 23014-10000-03481
- Plan Check / Job No.
- B23LA16128
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **E plan** New 2-STORY ADU addition to (E) detached GARAGE PER LAMC 12.22 A.33 (c) AND (d) and reduction and extension of( E) 2 car garage into 1 car gage
- Permit Issued
- Issued on 7/9/2024
- Issuing Office
- Current Status
- CofO Issued on 1/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2023 | YASHAR EMAMI |
| Corrections Issued | 9/27/2023 | YASHAR EMAMI |
| Re-Submittal Required | 10/2/2023 | REZA HAGHIGHAT |
| Re-Submitted | 10/12/2023 | YASHAR EMAMI |
| Corrections Issued 2 | 10/12/2023 | YASHAR EMAMI |
| Submitted for Second Quality Review | 10/12/2023 | YASHAR EMAMI |
| Quality Review Completed | 10/12/2023 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 4/9/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 5/14/2024 | YASHAR EMAMI |
| Plan Check Approved | 6/14/2024 | YASHAR EMAMI |
| Issued | 7/9/2024 | APPLICANT |
| CofO in Progress | 1/20/2026 | FREDDIE RIVERA |
| Permit Finaled | 1/21/2026 | DEROLD HAUFF |
| CofO Issued | 1/21/2026 | DEROLD HAUFF |
| Permit Finaled | 1/21/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/13/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2023 | JEANIE LAM |
| Sewer availability | Cleared | 11/16/2023 | JEANIE LAM |
| Construction near power lines | Cleared | 12/9/2023 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 2/21/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 2/26/2024 | JEANIE LAM |
| Tenant Habitability Plan | Cleared | 3/14/2024 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Bpc Development Inc; Lic. No.: 1059885-B | , |
| Contractor | Builder Point Construction; Lic. No.: 1059885-B | , |
| Engineer | Vega,, Cayetano Gonzalez; Lic. No.: C43117 | 9234 STAMPS AVE DOWNEY, CA 90240 |
| Engineer | Vega,, Cayetano Gonzalez; Lic. No.: NA43117 | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/18/2024 | Conditional Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 12/2/2024 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2024 | Partial Approval | ANTHONY RAMOS |
| ELECTRICAL-Rough | 1/22/2025 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 1/22/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 1/22/2025 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/3/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 2/3/2025 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/25/2025 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 2/25/2025 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 2/25/2025 | Approved | FREDDIE RIVERA |
| Insulation | 3/10/2025 | Corrections Issued | FREDDIE RIVERA |
| Interior/Exterior Lathing | 3/10/2025 | Partial Approval | FREDDIE RIVERA |
| Special/Order Compliance | 3/10/2025 | Partial Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/12/2025 | Approved | FREDDIE RIVERA |
| Insulation | 3/12/2025 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 3/24/2025 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 4/17/2025 | Not Ready for Inspection | ALEX COLIN |
| Shower Pan | 4/17/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 4/22/2025 | Approved | FREDDIE RIVERA |
| Gas Test | 7/3/2025 | Partial Approval | WILLIAM SIERRA |
| Sewer | 7/3/2025 | Approved | WILLIAM SIERRA |
| Underground Mechanical | 7/3/2025 | Partial Approval | WILLIAM SIERRA |
| ELECTRICAL-Final | 10/15/2025 | Approved | FREDDIE RIVERA |
| HVAC-Final | 10/15/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 10/15/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 11/20/2025 | Approved | LILIANA PORTILLO |
| Service/Power Release | 11/20/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 1/12/2026 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/12/2026 | Approved | FREDDIE RIVERA |
| Green Building Final | 1/12/2026 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 1/12/2026 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 1/12/2026 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 1/12/2026 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 1/12/2026 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 1/12/2026 | Partial Inspection | OSVALDO PARAMO |
| Final | 1/16/2026 | OK to Issue CofO | FREDDIE RIVERA |
| Service/Power Release | 1/16/2026 | Approved | FREDDIE RIVERA |