547 W 108TH ST 90044

Certificate Information: 547 W 108TH ST 90044

Application / Permit
23014-10000-03473
Plan Check / Job No.
B23LA16101
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED GARAGE CONVERSION AND ADDITION TO CREATE A.D.U. PER STATE LAW. CONST. PER W.F.P.P.
Permit Issued
Issued on 12/19/2023
Issuing Office
Metro
Current Status
CofO Issued on 8/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/29/2023 APPLICANT
Assigned to Plan Check Engineer 9/6/2023 LAWRENCE QUIRANTE
Corrections Issued 9/6/2023 LAWRENCE QUIRANTE
Building Plans Picked Up 9/8/2023 APPLICANT
Plan Check Approved 12/15/2023 WEIJIAN HUANG
Plan Check Approved 12/15/2023 WEIJIAN HUANG
Issued 12/19/2023 APPLICANT
CofO in Progress 8/28/2024 JOSEPH MCGARRY
Permit Finaled 8/30/2024 ANSON MAGLASANG
CofO Issued 8/30/2024 ANSON MAGLASANG
Permit Finaled 8/30/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 9/15/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 9/15/2023 CELINA MORENO
Roof/Waste drainage to street Cleared 9/15/2023 CELINA MORENO
Sewer availability Cleared 9/15/2023 CELINA MORENO
Construction near power lines Cleared 12/5/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/22/2024 Partial Inspection JAMES CHAVEZ
ELECTRICAL-Rough 3/8/2024 Not Ready for Inspection JAMES CHAVEZ
Sewer 3/8/2024 Approved JAMES CHAVEZ
Underground Mechanical 3/8/2024 Approved JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 3/29/2024 Not Ready for Inspection JAMES CHAVEZ
Footing/Foundation/Slab 3/29/2024 Corrections Issued JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 4/3/2024 Approved JAMES CHAVEZ
ELECTRICAL-Rough 5/15/2024 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 5/15/2024 Partial Approval JAMES CHAVEZ
Gas Test 5/15/2024 Partial Approval JAMES CHAVEZ
HVAC-Rough 5/15/2024 Approved JAMES CHAVEZ
PLUMBING-Rough 5/15/2024 Approved JAMES CHAVEZ
Insulation 5/17/2024 Approved JAMES CHAVEZ
Interior/Exterior Lathing 5/17/2024 Partial Approval JAMES CHAVEZ
Drywall Nailing 5/22/2024 Approved JAMES CHAVEZ
Interior/Exterior Lathing 5/22/2024 Partial Approval JAMES CHAVEZ
Gas Test 7/5/2024 Approved ANSON MAGLASANG
BUILDING-Rough-Frame 8/19/2024 Approved JOSEPH MCGARRY
Final 8/19/2024 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 8/19/2024 Approved JOSEPH MCGARRY
Green Building Final 8/19/2024 Approved JOSEPH MCGARRY
Green Building Rough 8/19/2024 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 8/19/2024 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 8/19/2024 Approved JOSEPH MCGARRY
Final 8/27/2024 OK to Issue CofO JOSEPH MCGARRY