8720-8720 1/2 S RAMSGATE AVE 90045
Certificate Information: 8720-8720 1/2 S RAMSGATE AVE 90045
- Application / Permit
- 23014-10000-03459
- Plan Check / Job No.
- B23LA16060
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT AND PROPOSE A SECOND FLOOR ADDITION TO CREATE AN ADDITIONAL ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(D). TWO ADUS TOTAL.
- Permit Issued
- Issued on 8/21/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2023 | MICHAEL LOPEZ |
| Corrections Issued | 9/12/2023 | MICHAEL LOPEZ |
| Quality Review Completed | 9/15/2023 | KEN GILL |
| Building Plans Picked Up | 10/5/2023 | APPLICANT |
| Applicant returned to address corrections | 7/16/2024 | MICHAEL LOPEZ |
| Plan Check Approved | 8/19/2024 | MICHAEL LOPEZ |
| Issued | 8/21/2024 | APPLICANT |
| CofO in Progress | 4/24/2025 | JESUS PINEDA |
| Permit Finaled | 4/24/2025 | RICHARD STEINBACH |
| CofO Issued | 4/24/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/24/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 9/25/2023 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 9/25/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2023 | DARIN LAM |
| Sewer availability | Cleared | 10/23/2023 | DARIN LAM |
| Miscellaneous | Cleared | 11/17/2023 | DANIEL CORONADO |
| Hydrant and Access approval | Cleared | 12/2/2023 | JOHN CONNEALLY |
| Specific Plan | Cleared | 1/26/2024 | PEDRO AYALA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vo,, Tung Thanh; Lic. No.: C69546 | 11122 BIXLER CIRCLE GARDEN GROVE, CA 92840 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/4/2024 | Conditional Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 9/9/2024 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 9/9/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 9/9/2024 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2024 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Special/Order Compliance | 11/6/2024 | Partial Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Conditional Approval | TEMISTOCLES CAAL |
| Special/Order Compliance | 11/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 11/19/2024 | Partial Inspection | TEMISTOCLES CAAL |
| Special/Order Compliance | 11/19/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Gas Test | 12/5/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 12/5/2024 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 12/5/2024 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 12/5/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 12/18/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 12/18/2024 | Approved | TEMISTOCLES CAAL |
| Sewer | 12/18/2024 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 12/18/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 12/24/2024 | Approved | BOBBY KEY |
| Green Building Rough | 12/24/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 12/24/2024 | Approved | BOBBY KEY |
| Insulation | 1/7/2025 | Corrections Issued | JESUS PINEDA |
| Special/Order Compliance | 1/7/2025 | Partial Inspection | HERBERT GIRON |
| Special/Order Compliance | 1/7/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Drywall Nailing | 1/14/2025 | Approved | JAYLIN GRAVITTE |
| Insulation | 1/14/2025 | Approved | JAYLIN GRAVITTE |
| Special/Order Compliance | 1/14/2025 | Partial Inspection | BOBBY KEY |
| Drywall Nailing | 4/23/2025 | Approved | JESUS PINEDA |
| Final | 4/23/2025 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 4/23/2025 | Approved | JESUS PINEDA |
| Insulation | 4/23/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 4/23/2025 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 4/23/2025 | Approved | JESUS PINEDA |
| Smoke Detectors | 4/23/2025 | Approved | JESUS PINEDA |