4852 N HAYVENHURST AVE 91436
Certificate Information: 4852 N HAYVENHURST AVE 91436
- Application / Permit
- 23014-10000-03455
- Plan Check / Job No.
- B23LA16035
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: REMODEL WITH ADDITION OF (EAST) 5'-10" x 10'-7", IRREGULAR SHAPPED (NORTH) 52'-0 x 15'-9", AND IRREGULAR SHAPED (WEST) 21'-9" x 45'-9" TO (E) S.F.D. PER ENGINEERING
- Permit Issued
- Issued on 9/26/2023
- Issuing Office
- Current Status
- CofO Issued on 11/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 9/1/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 9/26/2023 | ALFRED RAMIREZ |
| Issued | 9/26/2023 | APPLICANT |
| CofO in Progress | 10/22/2024 | THOMAS FINNILA |
| Permit Finaled | 11/20/2024 | JOHN JANSON |
| CofO Issued | 11/20/2024 | JOHN JANSON |
| Permit Finaled | 11/20/2024 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/21/2023 | DAGOVERTO GUERRERO |
| Low Impact Development (LID) | Cleared | 9/22/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 9/22/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/5/2023 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 10/17/2023 | Partial Approval | VINCENT HANLEY |
| Insulation | 10/25/2023 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 10/25/2023 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2023 | Partial Approval | HORACE FULTZ |
| BUILDING-Rough-Frame | 1/8/2024 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/8/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 1/8/2024 | Approved | VINCENT HANLEY |
| Wood Frame | 1/8/2024 | Partial Approval | VINCENT HANLEY |
| Insulation | 1/16/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/24/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 1/24/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/24/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 1/24/2024 | Partial Approval | VINCENT HANLEY |
| Shower Pan | 1/24/2024 | Approved | VINCENT HANLEY |
| Wood Frame | 1/24/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 5/30/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 5/30/2024 | Approved | THOMAS FINNILA |
| Gas Test | 5/30/2024 | Approved | THOMAS FINNILA |
| HVAC-Final | 5/30/2024 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Final | 5/30/2024 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 5/30/2024 | SGSOV Not Ready | THOMAS FINNILA |
| ELECTRICAL-Final | 6/25/2024 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 6/25/2024 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 6/25/2024 | Approved | THOMAS FINNILA |
| Service/Power Release | 7/5/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 7/11/2024 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/11/2024 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 7/11/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Service/Power Release | 7/15/2024 | Approved | THOMAS FINNILA |
| Final | 7/31/2024 | Partial Approval | THOMAS FINNILA |
| Green Building Final | 7/31/2024 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/31/2024 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 7/31/2024 | Approved | THOMAS FINNILA |
| Final | 10/21/2024 | OK to Issue CofO | THOMAS FINNILA |