12717 W GILMORE AVE 90066
Certificate Information: 12717 W GILMORE AVE 90066
- Application / Permit
- 23014-10000-03446
- Plan Check / Job No.
- B23LA16011
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL TO EXISTING SFD
- Permit Issued
- Issued on 4/8/2025
- Issuing Office
- Current Status
- Issued on 4/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2023 | JOSEPH RAFOLS |
| Corrections Issued | 9/5/2023 | CARLOS MONTES |
| Quality Review Completed | 9/6/2023 | GARO TELMI |
| Applicant returned to address corrections | 12/11/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 1/28/2025 | CARLOS MONTES |
| Applicant returned to address corrections | 2/28/2025 | CARLOS MONTES |
| Applicant returned to address corrections | 3/27/2025 | CARLOS MONTES |
| Plan Check Approved | 4/1/2025 | JOSEPH RAFOLS |
| Issued | 4/8/2025 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 10/18/2023 | FREDDY GARCIA |
| Low Impact Development (LID) | Cleared | 5/2/2024 | ERNEST TSE |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2024 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 5/11/2024 | DARIN LAM |
| Sewer availability | Cleared | 5/11/2024 | DARIN LAM |
| Excavation more than 5-ft deep | Cleared | 4/1/2025 | CALOSHA APPROVED |
Contact Information
| Contractor | S M Development Company Inc; Lic. No.: 450270-B | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: NA67449 | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/18/2025 | Partial Approval | RUBEN RIVAS |
| Excavation/Setback/Form/Re-Bar | 7/7/2025 | Approved | RUBEN RIVAS |
| Underground Mechanical | 7/7/2025 | Approved | RUBEN RIVAS |
| Footing/Foundation/Slab | 7/17/2025 | Approved | RUBEN RIVAS |
| Grounding or Bonding | 7/17/2025 | Partial Approval | RUBEN RIVAS |
| Deputy Drilled-In Anchors | 7/24/2025 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2025 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 8/28/2025 | Corrections Issued | RUBEN RIVAS |
| PLUMBING-Rough | 9/4/2025 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2025 | Partial Approval | RUBEN RIVAS |
| ELECTRICAL-Rough | 9/25/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Underground Mechanical | 9/25/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 10/27/2025 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Rough | 10/27/2025 | Partial Approval | RUBEN RIVAS |
| Green Building Rough | 10/27/2025 | Approved | RUBEN RIVAS |
| HVAC-Rough | 10/27/2025 | Corrections Issued | RUBEN RIVAS |
| Interior/Exterior Lathing | 10/27/2025 | Partial Approval | RUBEN RIVAS |
| Wood Frame | 10/27/2025 | Corrections Issued | RUBEN RIVAS |
| BUILDING-Rough-Frame | 11/6/2025 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Rough | 11/6/2025 | Approved | RUBEN RIVAS |
| HVAC-Rough | 11/6/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 11/6/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Wood Frame | 11/6/2025 | Not Ready for Inspection | RUBEN RIVAS |
| BUILDING-Rough-Frame | 11/14/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 11/14/2025 | Partial Approval | RUBEN RIVAS |
| Wood Frame | 11/14/2025 | Approved | RUBEN RIVAS |
| Insulation | 12/9/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 12/15/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Drywall Nailing | 12/16/2025 | Approved | MICHAEL ALLEN |
| Shower Pan | 12/16/2025 | Approved | MICHAEL ALLEN |