1724 W 55TH ST 90062

Certificate Information: 1724 W 55TH ST 90062

Application / Permit
23014-10000-03424
Plan Check / Job No.
B23LA15923
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
GARAGE CONVERSION TO ADU PER STATE LAW
Permit Issued
Issued on 12/21/2023
Issuing Office
Metro
Current Status
CofO Issued on 2/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2023 APPLICANT
Assigned to Plan Check Engineer 9/2/2023 SAMUEL GONZALEZ
Corrections Issued 9/2/2023 SAMUEL GONZALEZ
Building Plans Picked Up 9/11/2023 APPLICANT
Plan Check Approved 12/21/2023 WEIJIAN HUANG
Issued 12/21/2023 APPLICANT
CofO in Progress 2/12/2025 BARRY HACHE
Permit Finaled 2/23/2025 DEROLD HAUFF
CofO Issued 2/23/2025 DEROLD HAUFF
Permit Finaled 2/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/26/2023 JEANIE LAM
Sewer availability Cleared 9/26/2023 JEANIE LAM
Community Plan Implem. Overlay Cleared 11/30/2023 MANERI ROMAN
Eng Process Fee Ord 176,300 Cleared 12/4/2023 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/3/2024 Not Ready for Inspection CRAIG DAVIS
Footing/Foundation/Slab 7/11/2024 Approved CRAIG DAVIS
PLUMBING-Rough 7/22/2024 Not Ready for Inspection ANTHONY EGSON
Sewer 7/22/2024 Corrections Issued ANTHONY EGSON
Sewer 8/9/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 8/16/2024 Corrections Issued CRAIG DAVIS
Sewer 8/16/2024 Corrections Issued CRAIG DAVIS
Deputy Drilled-In Anchors 8/19/2024 Conditional Approval CRAIG DAVIS
ELECTRICAL-Rough 8/30/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 8/30/2024 Corrections Issued CRAIG DAVIS
Wood Frame 8/30/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 11/18/2024 Partial Inspection MICHAEL LEWIS
BUILDING-Rough-Frame 12/6/2024 Partial Approval JOSE MACIAS
ELECTRICAL-Rough 12/6/2024 Approved JOSE MACIAS
HVAC-Rough 12/6/2024 Corrections Issued JOSE MACIAS
Interior/Exterior Lathing 12/6/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 12/12/2024 Approved CRAIG DAVIS
Green Building Rough 12/12/2024 Approved CRAIG DAVIS
HVAC-Rough 12/12/2024 Approved CRAIG DAVIS
PLUMBING-Rough 12/12/2024 Partial Approval CRAIG DAVIS
Drywall Nailing 12/17/2024 Approved BARRY HACHE
SGSOV-Seismic Gas S/O Valve 1/6/2025 SGSOV Not Ready BARRY HACHE
Gas Test 1/15/2025 No Access for Inspection BARRY HACHE
PLUMBING-Rough 1/15/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 1/15/2025 SGSOV Not Ready BARRY HACHE
SGSOV-Seismic Gas S/O Valve 1/21/2025 SGSOV Not Ready BARRY HACHE
Sewer 1/21/2025 Not Ready for Inspection BARRY HACHE
Underground Mechanical 1/21/2025 Partial Approval BARRY HACHE
Underground Mechanical 1/24/2025 Partial Approval BARRY HACHE
ELECTRICAL-Final 1/28/2025 Corrections Issued BARRY HACHE
Final 1/28/2025 Corrections Issued BARRY HACHE
Green Building Final 1/28/2025 Approved BARRY HACHE
HVAC-Final 1/28/2025 Approved BARRY HACHE
PLUMBING-Final 1/28/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 1/28/2025 SGSOV Not Ready BARRY HACHE
Smoke Detectors 1/28/2025 Approved BARRY HACHE
ELECTRICAL-Final 2/6/2025 Not Ready for Inspection BARRY HACHE
Final 2/6/2025 Corrections Issued BARRY HACHE
Gas Test 2/6/2025 Approved BARRY HACHE
PLUMBING-Final 2/6/2025 Not Ready for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 2/6/2025 SGSOV Not Ready BARRY HACHE
SGSOV-Seismic Gas S/O Valve 2/10/2025 SGSOV Not Ready BARRY HACHE
ELECTRICAL-Final 2/11/2025 Approved BARRY HACHE
Final 2/11/2025 OK to Issue CofO BARRY HACHE
HVAC-Final 2/11/2025 Approved BARRY HACHE
PLUMBING-Final 2/11/2025 Approved BARRY HACHE
SGSOV-Seismic Gas S/O Valve 2/11/2025 SGSOV Approved BARRY HACHE