1329 N ARMADALE AVE 90042
Certificate Information: 1329 N ARMADALE AVE 90042
- Application / Permit
- 23014-10000-03418
- Plan Check / Job No.
- B23LA15894
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and Remodel to (E) SFD w/Attached Carpot
- Permit Issued
- Issued on 3/5/2024
- Issuing Office
- Current Status
- Issued on 3/5/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2023 | DAVID CASTILLO |
| Corrections Issued | 8/29/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 10/26/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 10/30/2023 | HERNAN ARREOLA |
| Plan Check Approved | 3/3/2024 | HERNAN ARREOLA |
| Issued | 3/5/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2023 | AMBER CAMPBELL |
| Low Impact Development (LID) | Cleared | 10/24/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/24/2023 | AMBER CAMPBELL |
| Sewer availability | Cleared | 10/24/2023 | AMBER CAMPBELL |
| Grading Pre-Inspection | Cleared | 10/31/2023 | DAVID CASTILLO |
| GPI Written Notices | Cleared | 3/3/2024 | HERNAN ARREOLA |
Contact Information
| Architect | Fenlon,, Martin Richard; Lic. No.: NA29965 | , |
| Contractor | Eye 4 Design And Renovation; Lic. No.: 878235-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/26/2024 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 4/26/2024 | Partial Approval | LILIANA PORTILLO |
| Deputy Reinf. Concrete | 4/30/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 5/17/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Underground Mechanical | 5/17/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Rough | 6/3/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Wood Frame | 6/3/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 8/19/2024 | Approved | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 8/28/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 12/19/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/19/2024 | Partial Approval | THOMAS LOGRASSO |
| HVAC-Rough | 12/19/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/19/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/17/2025 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 1/17/2025 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 1/17/2025 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 1/17/2025 | Corrections Issued | CRAIG DAVIS |
| Rough-Elec/Plmb/HVAC | 1/17/2025 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 2/13/2025 | Not Ready for Inspection | CRAIG DAVIS |
| ELECTRICAL-Rough | 2/13/2025 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Rough | 2/13/2025 | Not Ready for Inspection | CRAIG DAVIS |
| HVAC-Rough | 2/13/2025 | Approved | CRAIG DAVIS |
| PLUMBING-Rough | 2/13/2025 | Partial Inspection | CRAIG DAVIS |
| Rough-Elec/Plmb/HVAC | 2/13/2025 | Not Ready for Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 3/11/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| ELECTRICAL-Rough | 3/11/2025 | Corrections Issued | DAVID WILLIAMS |
| Green Building Rough | 3/11/2025 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 3/11/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 3/11/2025 | Corrections Issued | DAVID WILLIAMS |
| Wood Frame | 3/11/2025 | Approved | DAVID WILLIAMS |
| Insulation | 3/26/2025 | Conditional Approval | DAVID WILLIAMS |
| Drywall Nailing | 4/11/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 5/1/2025 | Approved | REGINA MENDEZ |
| BUILDING-Rough-Frame | 10/2/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Final | 10/2/2025 | Approved | DAVID WILLIAMS |
| Final | 10/2/2025 | Corrections Issued | DAVID WILLIAMS |
| Footing/Foundation/Slab | 10/2/2025 | Approved | DAVID WILLIAMS |
| Green Building Final | 10/2/2025 | Approved | DAVID WILLIAMS |
| HVAC-Final | 10/2/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Final | 10/2/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 10/2/2025 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 10/2/2025 | Approved | DAVID WILLIAMS |