4011 E BAYWOOD ST 90039
Certificate Information: 4011 E BAYWOOD ST 90039
- Application / Permit
- 23014-10000-03417
- Plan Check / Job No.
- B23LA15886
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 24' X 32'6" ADDITION TO (E) DETACHED GARAGE TO BECOME (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 8/26/2024
- Issuing Office
- Current Status
- CofO Issued on 5/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2023 | WEIJIAN HUANG |
| Corrections Issued | 8/29/2023 | WEIJIAN HUANG |
| Applicant returned to address corrections | 9/26/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 8/14/2024 | MADISON ODELL |
| Plan Check Approved | 8/24/2024 | MADISON O'DELL |
| Issued | 8/26/2024 | APPLICANT |
| CofO in Progress | 5/16/2025 | NICHOLAS LOPEZ |
| No Progress | 5/17/2025 | DEROLD HAUFF |
| CofO in Progress | 5/17/2025 | DEROLD HAUFF |
| Permit Finaled | 5/23/2025 | DEROLD HAUFF |
| CofO Issued | 5/23/2025 | DEROLD HAUFF |
| Permit Finaled | 5/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 9/22/2023 | MAXFIELD VERMY |
| Address approval | Cleared | 9/23/2023 | TERRY PHAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2023 | TERRY PHAN |
| Sewer availability | Cleared | 9/26/2023 | TERRY PHAN |
| Construction near power lines | Cleared | 12/16/2023 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 7/31/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 8/2/2024 | JUSTIN BICOL |
Contact Information
| Contractor | The Adu Guys Com Inc; Lic. No.: 1071442-B | , |
| Contractor | The Adu Guys.Com Inc; Lic. No.: 1071442-B | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/12/2024 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 9/23/2024 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 9/24/2024 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/17/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 11/12/2024 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Partial Approval | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 12/17/2024 | Corrections Issued | THOMAS LOGRASSO |
| Underground Mechanical | 12/17/2024 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/18/2024 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 12/18/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Insulation | 12/23/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/2/2025 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 1/2/2025 | Approved | THOMAS LOGRASSO |
| Insulation | 1/2/2025 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 1/2/2025 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 1/28/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 5/12/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 5/12/2025 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Final | 5/12/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 5/12/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/12/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 5/12/2025 | Approved | NICHOLAS LOPEZ |
| Final | 5/16/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/16/2025 | SGSOV Approved | NICHOLAS LOPEZ |
| Service/Power Release | 5/16/2025 | Approved | NICHOLAS LOPEZ |