1510 N GILCREST DR 90210
Certificate Information: 1510 N GILCREST DR 90210
- Application / Permit
- 23014-10000-03405
- Plan Check / Job No.
- B23LA15809
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan***PROPOSED REMODEL AND ADDITION TO SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 1/9/2024
- Issuing Office
- Current Status
- Issued on 1/9/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2023 | SINA KHOSRAVI |
| Corrections Issued | 9/5/2023 | SINA KHOSRAVI |
| Quality Review Completed | 9/15/2023 | YOUNG KIM |
| Applicant returned to address corrections | 12/14/2023 | SINA KHOSRAVI |
| Plan Check Approved | 12/27/2023 | SINA KHOSRAVI |
| Issued | 1/9/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2023 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 9/18/2023 | ANTHONY MAINEZ |
| ZA Case | Cleared | 9/20/2023 | DALIA MOKAYED |
| ZA Case | Cleared | 9/20/2023 | DALIA MOKAYED |
| Low Impact Development (LID) | Cleared | 11/29/2023 | SAMUEL LINN |
| GPI Written Notices | Cleared | 12/21/2023 | SINA KHOSRAVI |
| Grading Pre-Inspection | Cleared | 12/21/2023 | SINA KHOSRAVI |
Contact Information
| Architect | Saez, Martinez De La Pedraja, Juan; Lic. No.: C38677 | 400 N AVE 53 LOS ANGELES, CA 90042 |
| Contractor | Boswell Construction Inc; Lic. No.: 934480-B | 14611 VENTURA BLVD 2ND FLOOR SHERMAN OAKS, CA 91403 |
| Engineer | Liston,, Leonard Irvin; Lic. No.: C93123 | 889 PIERCE COURT, SUITE 101 THOUSAND OAKS, CA 91360 |
| Engineer | Yamini,, Soly; Lic. No.: C33719 | 540 WARNER AVE LOS ANGELES, CA 90024 |
| Geologist | Feffer,, Joshua R; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/1/2024 | Partial Inspection | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 3/4/2024 | Partial Approval | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 3/14/2024 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/14/2024 | Partial Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/21/2024 | Approved | RAUL BARAJAS |
| Pre-Inspection | 3/21/2024 | Corrections Issued | RAUL BARAJAS |
| Deputy Reinf. Concrete | 4/3/2024 | Conditional Approval | RAUL BARAJAS |
| PLUMBING-Rough | 7/26/2024 | Partial Approval | RAUL BARAJAS |
| Deputy Wood Construction | 9/27/2024 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Approved | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 3/26/2025 | Conditional Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 4/18/2025 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 4/21/2025 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 4/28/2025 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 5/7/2025 | Partial Approval | DAVID WILLIAMS |
| Special/Order Compliance | 5/15/2025 | Corrections Issued | SCOTT FINNILA |
| Wood Frame | 5/15/2025 | Not Ready for Inspection | SCOTT FINNILA |
| Wood Frame | 5/19/2025 | Corrections Issued | RAUL BARAJAS |
| Insulation | 6/2/2025 | Approved | RAUL BARAJAS |
| Wood Frame | 6/2/2025 | Approved | RAUL BARAJAS |
| Drywall Nailing | 6/25/2025 | Approved | JOSH MEISTER |
| Shower Pan | 7/9/2025 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 8/12/2025 | Partial Approval | BRENDAN MORELLI |
| Interior/Exterior Lathing | 1/15/2026 | Approved | DAVID WILLIAMS |
| Underground Mechanical | 5/12/2026 | Partial Approval | BRENDAN MORELLI |