7995 W BRIAR SUMMIT DR 90046
Certificate Information: 7995 W BRIAR SUMMIT DR 90046
- Application / Permit
- 23014-10000-03381
- Plan Check / Job No.
- B23LA15681
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Enlarge current attached one car garage to (N) two car garage by increasing depth into (E) underfloor area and width by converting (E) habitable area to Garage area. (see comments)
- Permit Issued
- Issued on 11/7/2024
- Issuing Office
- Current Status
- CofO Issued on 9/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2023 | MINA HABIB |
| Corrections Issued | 9/18/2023 | MINA HABIB |
| Quality Review Completed | 9/19/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 10/17/2023 | MINA HABIB |
| Applicant returned to address corrections | 11/29/2023 | MINA HABIB |
| Applicant returned to address corrections | 12/6/2023 | MINA HABIB |
| Applicant returned to address corrections | 1/26/2024 | MINA HABIB |
| Applicant returned to address corrections | 2/5/2024 | MINA HABIB |
| Applicant returned to address corrections | 2/6/2024 | MINA HABIB |
| Applicant returned to address corrections | 2/15/2024 | MINA HABIB |
| Applicant returned to address corrections | 2/21/2024 | MINA HABIB |
| Applicant returned to address corrections | 4/3/2024 | MINA HABIB |
| Applicant returned to address corrections | 4/4/2024 | MINA HABIB |
| Applicant returned to address corrections | 4/5/2024 | MINA HABIB |
| Applicant returned to address corrections | 4/9/2024 | MINA HABIB |
| Applicant returned to address corrections | 4/25/2024 | MINA HABIB |
| Applicant returned to address corrections | 5/20/2024 | MINA HABIB |
| Applicant returned to address corrections | 5/21/2024 | MINA HABIB |
| Applicant returned to address corrections | 6/3/2024 | MINA HABIB |
| Applicant returned to address corrections | 6/4/2024 | MINA HABIB |
| Plan Check Approved | 6/5/2024 | MINA HABIB |
| Issued | 11/7/2024 | APPLICANT |
| CofO in Progress | 8/28/2025 | ROY SPAULDING |
| Permit Finaled | 9/2/2025 | DEROLD HAUFF |
| CofO Issued | 9/2/2025 | DEROLD HAUFF |
| Permit Finaled | 9/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/6/2023 | WALTER RAMIREZ |
| Construction within easement | Cleared | 10/6/2023 | WALTER RAMIREZ |
| Trees in Parkway | Cleared | 10/17/2023 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 10/22/2023 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2023 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 12/12/2023 | JUSTIN BICOL |
| Certificate of Compliance | Cleared | 12/13/2023 | SPENCER WEJROWSKI |
| Miscellaneous | Cleared | 12/13/2023 | SPENCER WEJROWSKI |
| Permit | Cleared | 12/19/2023 | DAVID VO |
| Specific Plan | Cleared | 1/17/2024 | TIFFANY CORRALES |
| Specific Plan | Cleared | 1/17/2024 | TIFFANY CORRALES |
| Grading Pre-Inspection | Cleared | 4/9/2024 | MINA HABIB |
| Green Code | Cleared | 4/9/2024 | MINA HABIB |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Aparicio,, Daniel Gonzalo; Lic. No.: C92121 | 19332 AVENIDA DEL SOL WALNUT, CA 91789 |
| Engineer | Jardine, Prouty, Kyle Addison; Lic. No.: C95048 | 2239 STATE AVE UNIT B COSTA MESA, CA 92627 |
| Engineer | Rowlands,, James; Lic. No.: GE740 | 10954 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
| Geologist | Nguyen,, An; Lic. No.: EG2468 | 5913 SATURN STREET LOS ANGELES, CA 90035 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/17/2025 | Corrections Issued | ROY SPAULDING |
| Deputy Drilled-In Anchors | 1/21/2025 | Conditional Approval | ROY SPAULDING |
| Deputy Reinf. Concrete | 1/21/2025 | Conditional Approval | ROY SPAULDING |
| Deputy Shotcrete | 1/21/2025 | Conditional Approval | ROY SPAULDING |
| Footing/Foundation/Slab | 2/12/2025 | Partial Approval | ROY SPAULDING |
| Deputy Drilled-In Anchors | 2/27/2025 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 2/28/2025 | Partial Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 3/6/2025 | Partial Approval | ROY SPAULDING |
| Deputy Reinf. Concrete | 3/7/2025 | Conditional Approval | ROY SPAULDING |
| Deputy Drilled-In Anchors | 3/18/2025 | Conditional Approval | ROY SPAULDING |
| Deputy Reinf. Concrete | 3/18/2025 | Conditional Approval | ROY SPAULDING |
| Footing/Foundation/Slab | 3/19/2025 | Partial Approval | ROY SPAULDING |
| BUILDING-Rough-Frame | 3/24/2025 | Approved | ROY SPAULDING |
| Green Building Rough | 3/24/2025 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 3/27/2025 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 3/27/2025 | Approved | ROY SPAULDING |
| Insulation | 4/10/2025 | Approved | ROY SPAULDING |
| Drywall Nailing | 4/18/2025 | Approved | ROY SPAULDING |
| Pre-Inspection | 6/16/2025 | Corrections Issued | ROY SPAULDING |
| Final | 8/27/2025 | OK to Issue CofO | ROY SPAULDING |
| Footing/Foundation/Slab | 8/27/2025 | Approved | ROY SPAULDING |
| Green Building Final | 8/27/2025 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 8/27/2025 | SGSOV Approved | ROY SPAULDING |
| Smoke Detectors | 8/27/2025 | Approved | ROY SPAULDING |