8304 S ZITOLA TER 90293
Certificate Information: 8304 S ZITOLA TER 90293
- Application / Permit
- 23014-10000-03372
- Plan Check / Job No.
- B23LA15608
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan MAJOR INTERIOR REMODEL OF (E) FIRST FLOOR TO CREATE JR MASTER SUITE AND PROVIDE STAIR ACCESS,INTERIOR REMODEL TO ENTRY FOYER & KITCHEN,(N) 2ND FLOOR ADDITION TO PROVIDE MASTER SUITE AND LAUNDRY RM,(N) DECK OVER FIRST FLOOR LIVING AREA AND ALL (E) WINDOWS TO BE REPLACED.
- Permit Issued
- Issued on 1/15/2024
- Issuing Office
- Current Status
- CofO Issued on 12/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/7/2023 | MICHAEL LOPEZ |
| Corrections Issued | 9/20/2023 | MICHAEL LOPEZ |
| Quality Review Completed | 9/20/2023 | GARO TELMI |
| Applicant returned to address corrections | 10/2/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 11/9/2023 | MICHAEL LOPEZ |
| Issued | 1/15/2024 | APPLICANT |
| CofO in Progress | 12/19/2025 | JESUS PINEDA |
| Permit Finaled | 12/23/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/23/2025 | RICHARD STEINBACH |
| CofO Issued | 12/23/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 9/13/2023 | NELSON RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2023 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 9/21/2023 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 9/21/2023 | FREDDY GARCIA |
| Roof/Waste drainage to street | Cleared | 9/22/2023 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 9/25/2023 | RUSSELL BONVOULOIR |
| Low Impact Development (LID) | Cleared | 10/26/2023 | ROGELIO CORTES |
| GPI Written Notices | Cleared | 11/9/2023 | MATTHEW JENKINS |
Contact Information
| Architect | Song,, Michael; Lic. No.: NA32566 | , |
| Contractor | Kor Design Build; Lic. No.: 1026877-B | , |
| Engineer | Kazemi,, Milad; Lic. No.: NA92143 | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 3/14/2024 | Conditional Approval | BOBBY KEY |
| PLUMBING-Rough | 4/2/2024 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 4/9/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Corrections Issued | BOBBY KEY |
| Deputy Wood Construction | 5/9/2024 | Conditional Approval | BOBBY KEY |
| Deputy Wood Construction | 6/18/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 7/5/2024 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2024 | Partial Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 7/24/2024 | Approved | BOBBY KEY |
| Deputy Reinf. Concrete | 7/26/2024 | Conditional Approval | BOBBY KEY |
| PLUMBING-Rough | 8/28/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 8/30/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 8/30/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 8/30/2024 | Approved | BOBBY KEY |
| Special/Order Compliance | 8/30/2024 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 9/10/2024 | Approved | BOBBY KEY |
| Green Building Rough | 9/10/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 9/10/2024 | Partial Approval | BOBBY KEY |
| Insulation | 9/24/2024 | Approved | BOBBY KEY |
| Special/Order Compliance | 9/24/2024 | Corrections Issued | BOBBY KEY |
| Shower Pan | 9/27/2024 | Corrections Issued | BOBBY KEY |
| Drywall Nailing | 10/7/2024 | Not Ready for Inspection | BOBBY KEY |
| Shower Pan | 10/7/2024 | Not Ready for Inspection | BOBBY KEY |
| Drywall Nailing | 10/10/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/10/2024 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 10/10/2024 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 10/16/2024 | Approved | BOBBY KEY |
| Shower Pan | 10/16/2024 | Approved | BOBBY KEY |
| HVAC-Final | 1/21/2025 | Conditional Approval | EUGENE CASSIDY |
| ELECTRICAL-Final | 3/10/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 3/10/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 3/10/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 3/10/2025 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 3/10/2025 | Approved | JESUS PINEDA |
| Smoke Detectors | 3/10/2025 | Approved | JESUS PINEDA |
| Final | 5/7/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 5/7/2025 | Approved | JESUS PINEDA |
| Final | 12/19/2025 | OK to Issue CofO | JESUS PINEDA |