131 S VISTA ST 90036

Certificate Information: 131 S VISTA ST 90036

Application / Permit
23014-10000-03363
Plan Check / Job No.
B23LA15591
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SFD
Permit Issued
Issued on 5/10/2024
Issuing Office
Current Status
Issued on 5/10/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/21/2023 APPLICANT
Assigned to Plan Check Engineer 8/24/2023 CARLOS MONTES
Corrections Issued 8/27/2023 CARLOS MONTES
Quality Review Completed 8/31/2023 GARO TELMI
Applicant returned to address corrections 12/8/2023 CARLOS MONTES
Plan Check Approved 5/10/2024 CARLOS MONTES
Issued 5/10/2024 APPLICANT

Permit Application Clearance Information

CPC Cleared 8/31/2023 YINGSHI HUANG
CPC Cleared 8/31/2023 YINGSHI HUANG
Miscellaneous Cleared 8/31/2023 YINGSHI HUANG
Miscellaneous Cleared 8/31/2023 YINGSHI HUANG
Eng Process Fee Ord 176,300 Cleared 9/7/2023 NEIL TUANO
Roof/Waste drainage to street Cleared 9/7/2023 NEIL TUANO
Sewer availability Cleared 9/7/2023 NEIL TUANO
Low Impact Development (LID) Cleared 1/26/2024 PATRICK LOPEZ
HPOZ Cleared 5/1/2024 DAMIAN GATTO
Miscellaneous Cleared 5/1/2024 DAMIAN GATTO

Contact Information

Architect Rabin,, Daniel H; Lic. No.: NA36893       ,
Contractor Luis Chavez Construction Inc; Lic. No.: 1024942-B       ,
Engineer Phillips,, Craig; Lic. No.: NA69673       ,

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/7/2025 Approved JOSE MACIAS
Footing/Foundation/Slab 4/22/2025 Partial Approval JOSE MACIAS
METHANE-Barrier 4/22/2025 Not Ready for Inspection JOSE MACIAS
METHANE-Subgrade 4/22/2025 Not Ready for Inspection JOSE MACIAS
Underground Mechanical 5/6/2025 Approved JOSE MACIAS
Deputy Reinf. Concrete 5/7/2025 Conditional Approval JOSE MACIAS
Footing/Foundation/Slab 5/19/2025 Approved JOSE MACIAS
METHANE-Barrier 5/19/2025 Approved JOSE MACIAS
METHANE-Subgrade 5/19/2025 Approved JOSE MACIAS
Special/Order Compliance 5/20/2025 Partial Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/23/2025 Partial Approval JOSE MACIAS
Excavation/Setback/Form/Re-Bar 6/26/2025 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 9/17/2025 Partial Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 10/1/2025 Not Ready for Inspection BRENDAN MORELLI
Deputy Wood Construction 10/3/2025 Conditional Approval JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Partial Approval JOSH MEISTER
Special/Order Compliance 10/3/2025 Corrections Issued JOSH MEISTER
HVAC-Rough 5/7/2026 Approved JOSH MEISTER
PLUMBING-Rough 5/7/2026 Approved JOSH MEISTER
BUILDING-Rough-Frame 5/8/2026 Approved Pending GreenApproval JOSH MEISTER
ELECTRICAL-Rough 5/8/2026 Approved JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 5/8/2026 Approved JOSH MEISTER
Green Building Rough 5/8/2026 Not Ready for Inspection JOSH MEISTER
METHANE-Rough 5/8/2026 Approved JOSH MEISTER
Insulation 5/21/2026 Approved JOSH MEISTER
Interior/Exterior Lathing 5/27/2026 Not Ready for Inspection JOSH MEISTER
Interior/Exterior Lathing 5/29/2026 Partial Approval JOSH MEISTER
Drywall Nailing 6/1/2026 Approved JOSH MEISTER