5734 N SALOMA AVE 91411

Certificate Information: 5734 N SALOMA AVE 91411

Application / Permit
23014-10000-03303
Plan Check / Job No.
B23LA15344
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 17'-8" x 12'-6' 1/2" ADDITION TO (E) SFD AND CONVERT (E) ATTACHED GARAGE INTO A HABITABLE SPACE. PART 1 OF 2
Permit Issued
Issued on 1/17/2024
Issuing Office
Current Status
CofO Issued on 9/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2023 APPLICANT
Assigned to Plan Check Engineer 8/22/2023 MIROOSH KHACHATOORIAN
Corrections Issued 8/23/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 10/19/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 1/11/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 1/16/2024 MIROOSH KHACHATOORIAN
Issued 1/17/2024 APPLICANT
CofO in Progress 8/26/2024 RYAN SALAZAR
Permit Finaled 9/12/2024 DANIEL ORRANTE
CofO Issued 9/12/2024 DANIEL ORRANTE
Permit Finaled 9/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/15/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 9/15/2023 CARLOS AGUILERA

Contact Information

Architect Salcedo,, Glen Charles; Lic. No.: NA33143       ,
Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/8/2024 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 3/8/2024 Approved RYAN SALAZAR
Footing/Foundation/Slab 3/8/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 3/15/2024 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 3/21/2024 Partial Approval RYAN SALAZAR
PLUMBING-Rough 3/21/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 3/28/2024 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 4/4/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 4/4/2024 Approved RYAN SALAZAR
HVAC-Rough 4/4/2024 Approved RYAN SALAZAR
Insulation 4/11/2024 Conditional Approval JOHN COLEMAN
Interior/Exterior Lathing 4/11/2024 Partial Approval JOHN COLEMAN
Wood Frame 4/11/2024 Approved JOHN COLEMAN
Drywall Nailing 4/15/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/26/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 7/11/2024 Approved RYAN SALAZAR
ELECTRICAL-Final 7/11/2024 Approved RYAN SALAZAR
Final 7/11/2024 Corrections Issued RYAN SALAZAR
Green Building Final 7/11/2024 Approved RYAN SALAZAR
Green Building Rough 7/11/2024 Approved RYAN SALAZAR
HVAC-Final 7/11/2024 Approved RYAN SALAZAR
PLUMBING-Final 7/11/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 7/11/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 7/11/2024 Approved RYAN SALAZAR
Final 8/26/2024 OK to Issue CofO RYAN SALAZAR