3144 W 74TH ST 90043
Certificate Information: 3144 W 74TH ST 90043
- Application / Permit
- 23014-10000-03300
- Plan Check / Job No.
- B23LA15337
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE (306sf) TO A NEW SINGLE STORY ADU WITH ADDTION PER ENGINEER DETAILS (800 SF max New Construction per State Law, CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g))
- Permit Issued
- Issued on 4/12/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2023 | AUNG SOE |
| Corrections Issued | 8/29/2023 | AUNG SOE |
| Building Plans Picked Up | 8/31/2023 | APPLICANT |
| Plan Check Approved | 4/11/2024 | JOSEPH RAFOLS |
| Issued | 4/12/2024 | APPLICANT |
| CofO in Progress | 7/22/2025 | MICHAEL LEWIS |
| Permit Finaled | 7/24/2025 | DEROLD HAUFF |
| CofO Issued | 7/24/2025 | DEROLD HAUFF |
| Permit Finaled | 7/24/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/15/2023 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 9/15/2023 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 10/11/2023 | JESSICA OPINION |
| Sewer availability | Cleared | 10/11/2023 | JESSICA OPINION |
| Construction near power lines | Cleared | 2/21/2024 | RIDWAN HARDY |
Contact Information
| Architect | Scrafano,, Elissa F; Lic. No.: C26071 | 163 N SYCAMORE LOS ANGELES, CA 90036 |
| Contractor | A R M Builders Inc; Lic. No.: 915352-B | 1080 S LA CIENEGA #311 LOS ANGELES, CA 90035 |
| Engineer | Lycklama,, James Heinz; Lic. No.: L7525 | 32218 N BIG OAK LN CASTAIC, CA 91384 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/24/2024 | Approved | JOSE MACIAS |
| Deputy Drilled-In Anchors | 6/6/2024 | Approved | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 6/6/2024 | Corrections Issued | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 6/17/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 7/29/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 7/29/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 7/29/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 7/29/2024 | Approved | JOSE MACIAS |
| Insulation | 8/9/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 8/9/2024 | Conditional Approval | ALEX COLIN |
| Shower Pan | 8/9/2024 | Approved | ALEX COLIN |
| Drywall Nailing | 8/14/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 8/14/2024 | Approved | ALEX COLIN |
| Underground Mechanical | 9/13/2024 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 9/20/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 11/20/2024 | Approved | AMIR NAZARIAN |
| Final | 11/20/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 11/20/2024 | Approved | AMIR NAZARIAN |
| Green Building Final | 11/20/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 11/20/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 11/20/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Smoke Detectors | 11/20/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 11/25/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 11/25/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 11/25/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Smoke Detectors | 11/25/2024 | Corrections Issued | AMIR NAZARIAN |
| Pre-Inspection | 11/27/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 5/19/2025 | Corrections Issued | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Not Required | WAYNE REGESTER |
| Smoke Detectors | 5/19/2025 | Conditional Approval | WAYNE REGESTER |
| Final | 6/6/2025 | Partial Approval | WAYNE REGESTER |
| Smoke Detectors | 6/6/2025 | Approved | WAYNE REGESTER |
| Final | 7/22/2025 | Conditional Approval | MICHAEL LEWIS |
| Final | 7/22/2025 | OK to Issue CofO | MICHAEL LEWIS |