5309 W LA MIRADA AVE 90029

Certificate Information: 5309 W LA MIRADA AVE 90029

Application / Permit
23014-10000-03297
Plan Check / Job No.
B23LA15320
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: ADDITION OF (N) DETACHED 27'-6" x 23'-2" ACCESSORY DWELLING UNIT WITH FRONT PORCH ATTACHED TO (E) DETACHED GARAGE PER ORDINANCE.
Permit Issued
Issued on 11/22/2024
Issuing Office
Current Status
Issued on 11/22/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/20/2023 APPLICANT
Assigned to Plan Check Engineer 9/22/2023 ALFRED RAMIREZ
Corrections Issued 1/3/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 8/23/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 10/29/2024 LUISANGEL VALENZUELA
Plan Check Approved 10/31/2024 DANIEL SMILEY
Issued 11/22/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/6/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 3/28/2024 CHRISTINA BRACO
Sewer availability Cleared 3/28/2024 CHRISTINA BRACO
Low Impact Development (LID) Cleared 8/16/2024 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 8/19/2024 RYAN CASTRO

Contact Information

Contractor Grid Line Structures Inc; Lic. No.: 1070999-B       ,
Engineer Burnazyan,, Gegam; Lic. No.: NA76761       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/11/2024 Approved CRAIG VAUGHAN
Deputy Drilled-In Anchors 12/16/2024 Conditional Approval NICHOLAS LOPEZ
Excavation/Setback/Form/Re-Bar 12/24/2024 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 12/24/2024 Approved CRAIG VAUGHAN
Gas Test 1/13/2025 Partial Approval ROY SPAULDING
PLUMBING-Rough 1/13/2025 Partial Approval ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 2/11/2025 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 2/11/2025 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 2/20/2025 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 2/20/2025 Approved CRAIG VAUGHAN
Shower Pan 2/20/2025 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 3/4/2025 Corrections Issued CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Partial Approval CRAIG VAUGHAN
Shower Pan 3/4/2025 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 3/6/2025 Approved CRAIG VAUGHAN
Deputy Wood Construction 3/6/2025 Conditional Approval CRAIG VAUGHAN
ELECTRICAL-Rough 3/6/2025 Partial Approval CRAIG VAUGHAN
MERV13>=Rough 3/6/2025 Approved CRAIG VAUGHAN
Insulation 3/11/2025 No Access for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 3/11/2025 No Access for Inspection CRAIG VAUGHAN
Insulation 3/13/2025 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 3/13/2025 Partial Approval CRAIG VAUGHAN
Drywall Nailing 3/20/2025 Approved BRENDAN MORELLI
Interior/Exterior Lathing 5/14/2025 Approved CRAIG VAUGHAN