678 W 16TH ST 1-6 90731
Certificate Information: 678 W 16TH ST 1-6 90731
- Application / Permit
- 23014-10000-03279
- Plan Check / Job No.
- B23LA15271
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ADU ADDITION ON 2ND FLOOR OF EXISTING APARTMENT
- Permit Issued
- Issued on 4/30/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2023 | HERNAN ARREOLA |
| Corrections Issued | 9/10/2023 | HERNAN ARREOLA |
| Quality Review Completed | 9/12/2023 | PETER KIM |
| Building Plans Picked Up | 9/18/2023 | APPLICANT |
| Plan Check Approved | 4/30/2024 | EUGENE BARBEAU |
| Issued | 4/30/2024 | APPLICANT |
| Permit Finaled | 10/17/2025 | DAVID TSAU |
| CofO Issued | 10/17/2025 | DAVID TSAU |
| Permit Finaled | 10/17/2025 | DAVID TSAU |
Permit Application Clearance Information
| Green Code | Cleared | 9/19/2023 | NEGAR NEJAD |
| Address approval | Cleared | 10/12/2023 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2023 | KHAING AYE |
| Sewer availability | Cleared | 10/12/2023 | KHAING AYE |
| Tenant Habitability Plan | Cleared | 11/20/2023 | ISMAEL HERNANDEZ |
| Low Impact Development (LID) | Cleared | 12/5/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 12/8/2023 | KHAING AYE |
| Miscellaneous | Cleared | 1/19/2024 | HERNAN ARREOLA |
Contact Information
| Contractor | Mg Elite Construction; Lic. No.: 1098511-B | 400 N VALENCIA ST LA HABRA, CA 90631 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 8/30/2024 | Approved | AMANUEL BERHE |
| Pre-Inspection | 8/30/2024 | Partial Approval | AMANUEL BERHE |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Approved | AMANUEL BERHE |
| Wood Frame | 11/4/2024 | Not Ready for Inspection | JOEY BUCHANAN |
| Pre-Inspection | 11/6/2024 | Corrections Issued | JOEY BUCHANAN |
| Insulation | 11/12/2024 | Approved | JOEY BUCHANAN |
| Wood Frame | 11/12/2024 | Partial Approval | JOEY BUCHANAN |
| Drywall Nailing | 11/18/2024 | Approved | JOEY BUCHANAN |
| Wood Frame | 11/18/2024 | Corrections Issued | JOEY BUCHANAN |
| Interior/Exterior Lathing | 12/2/2024 | Approved | MICHAEL PETRUSKO |
| Interior/Exterior Lathing | 12/19/2024 | Approved | MICHAEL PETRUSKO |
| Final | 3/18/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Footing/Foundation/Slab | 3/18/2025 | Approved | MICHAEL PETRUSKO |
| Green Building Final | 3/18/2025 | Approved | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 3/18/2025 | SGSOV Approved | MICHAEL PETRUSKO |
| Smoke Detectors | 3/18/2025 | Approved | MICHAEL PETRUSKO |
| Wood Frame | 3/18/2025 | Approved | MICHAEL PETRUSKO |
| Final | 4/10/2025 | Corrections Issued | JOEY BUCHANAN |
| Final | 4/18/2025 | Conditional Approval | JOEY BUCHANAN |
| Final | 9/23/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Final | 10/7/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Final | 10/9/2025 | Conditional Approval | MICHAEL PETRUSKO |