1713 N ISLAND AVE 90744
Certificate Information: 1713 N ISLAND AVE 90744
- Application / Permit
- 23014-10000-03266
- Plan Check / Job No.
- B23LA15206
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan CONVERT (E) DETACHED GARAGE (660 SF) AND (N) ADDITION (60 SF) TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/8/2024
- Issuing Office
- Current Status
- CofO Issued on 3/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2023 | ISIS ARGUETA |
| Corrections Issued | 8/22/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 12/20/2023 | ISIS ARGUETA |
| Plan Check Approved | 1/3/2024 | ISIS ARGUETA |
| Issued | 1/8/2024 | APPLICANT |
| CofO in Progress | 3/16/2026 | EUGENE CASSIDY |
| Permit Finaled | 3/17/2026 | ANSON MAGLASANG |
| CofO Issued | 3/17/2026 | ANSON MAGLASANG |
| Permit Finaled | 3/17/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 12/6/2023 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2023 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 12/6/2023 | ERIK BEASLEY |
| Sewer availability | Cleared | 12/6/2023 | ERIK BEASLEY |
| ZA Case | Cleared | 12/6/2023 | DANIEL CORONADO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tiongco,, John Lazarraga; Lic. No.: C70915 | 17715 CANEHILL AVE BELLFLOWER, CA 90706 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/24/2024 | Corrections Issued | JAMES CHAVEZ |
| PLUMBING-Rough | 5/24/2024 | Partial Approval | JAMES CHAVEZ |
| Sewer | 5/24/2024 | Approved | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 5/28/2024 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/17/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 9/18/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2024 | Partial Approval | JOSEPH MCGARRY |
| Gas Test | 9/18/2024 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 9/18/2024 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 1/30/2025 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 1/30/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Rough | 1/30/2025 | Approved | EUGENE CASSIDY |
| Insulation | 1/30/2025 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 1/30/2025 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 2/18/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 2/18/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 2/18/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Insulation | 2/24/2025 | Corrections Issued | EUGENE CASSIDY |
| Interior/Exterior Lathing | 2/24/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Insulation | 2/28/2025 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 3/7/2025 | Approved | EUGENE CASSIDY |
| Shower Pan | 8/25/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 9/12/2025 | Approved | EUGENE CASSIDY |
| Final | 11/4/2025 | Corrections Issued | EUGENE CASSIDY |
| Gas Test | 11/4/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 11/4/2025 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 11/4/2025 | Approved | EUGENE CASSIDY |
| Final | 11/26/2025 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 11/26/2025 | SGSOV Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 3/16/2026 | Approved | EUGENE CASSIDY |
| Final | 3/16/2026 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 3/16/2026 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 3/16/2026 | Approved | EUGENE CASSIDY |