514 N COMMONWEALTH AVE 90004

Certificate Information: 514 N COMMONWEALTH AVE 90004

Application / Permit
23014-10000-03250
Plan Check / Job No.
B23LA15110
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition of 280 SF deck to rear of existing 2-story single family dwelling with exterior alterations. All work per engineer.
Permit Issued
Issued on 8/31/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2023 APPLICANT
Assigned to Plan Check Engineer 8/21/2023 JOSEPH RAFOLS
Corrections Issued 8/23/2023 JOSEPH RAFOLS
Building Plans Picked Up 8/25/2023 APPLICANT
Plan Check Approved 8/31/2023 VICTOR CHEN
Issued 8/31/2023 APPLICANT
CofO in Progress 5/6/2024 FREDDIE RIVERA
CofO Issued 5/16/2024 DEROLD HAUFF
Permit Finaled 5/16/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/25/2023 STEVEN JIN
Roof/Waste drainage to street Cleared 8/25/2023 STEVEN JIN

Contact Information

Architect Reynolds,, James Rory; Lic. No.: C34771 1649 LYMAN PLACE      LOS ANGELES, CA 90027
Contractor Owner-Builder       ,
Engineer Andrada,, Aprile; Lic. No.: C81097 27240 TURNBERRY LANE      VALENCIA, CA 91355

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/10/2023 Approved FREDDIE RIVERA
Deputy Drilled-In Anchors 10/23/2023 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 11/1/2023 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 11/1/2023 Approved FREDDIE RIVERA
Green Building Rough 11/1/2023 Partial Inspection FREDDIE RIVERA
MERV13>=Rough 11/1/2023 Partial Inspection FREDDIE RIVERA
Insulation 11/3/2023 Approved JEFFREY MEAD
Deputy Wood Construction 11/13/2023 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 11/15/2023 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 11/15/2023 Approved FREDDIE RIVERA
Green Building Rough 11/15/2023 Approved FREDDIE RIVERA
MERV13>=Rough 11/15/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 11/29/2023 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/11/2024 SGSOV Not Ready FREDDIE RIVERA
Final 4/19/2024 Corrections Issued FREDDIE RIVERA
Green Building Final 4/19/2024 Approved FREDDIE RIVERA
MERV13>=Final 4/19/2024 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 4/19/2024 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 4/19/2024 Approved FREDDIE RIVERA
Final 5/6/2024 OK to Issue CofO FREDDIE RIVERA