2825 S CLUNE AVE 90291

Certificate Information: 2825 S CLUNE AVE 90291

Application / Permit
23014-10000-03227
Plan Check / Job No.
B23LA15003
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
convert (e) garage into ADU, storage at 2nd flr per LAMC 12.22 A.33 R3/U Occupancy
Permit Issued
Issued on 5/14/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/11/2023 APPLICANT
Assigned to Plan Check Engineer 8/31/2023 KELVIN CHUONG
Corrections Issued 9/12/2023 KELVIN CHUONG
Quality Review Completed 9/15/2023 KEN GILL
Building Plans Picked Up 9/20/2023 APPLICANT
Applicant returned to address corrections 11/2/2023 KELVIN CHUONG
Plan Check Approved 12/21/2023 KELVIN CHUONG
Issued 5/14/2024 APPLICANT
Permit Finaled 5/27/2025 RICHARD STEINBACH
CofO Issued 5/27/2025 RICHARD STEINBACH
Permit Finaled 5/27/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 9/18/2023 DARIN LAM
Roof/Waste drainage to street Cleared 9/18/2023 DARIN LAM
Sewer availability Cleared 9/18/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 9/20/2023 DARIN LAM
Specific Plan Cleared 11/7/2023 PEDRO AYALA
Specific Plan Cleared 11/7/2023 PEDRO AYALA
Coastal Zone Cleared 11/29/2023 MATHEW QUAN
Specific Plan Cleared 11/29/2023 MATHEW QUAN
Flood clearance Cleared 12/12/2023 SAMSON WONG

Contact Information

Contractor The Curtis Co; Lic. No.: 533785-B 26952 DE BERRY DRIVE      CALABASAS HILLS, CA 91301

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/16/2024 Partial Inspection HERBERT GIRON
Footing/Foundation/Slab 5/20/2024 Corrections Issued HERBERT GIRON
Deputy Drilled-In Anchors 5/21/2024 Conditional Approval HERBERT GIRON
Footing/Foundation/Slab 5/23/2024 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 6/10/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 6/20/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 6/20/2024 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 6/24/2024 Partial Approval HERBERT GIRON
Insulation 6/24/2024 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 7/3/2024 Partial Approval HERBERT GIRON
Underground Mechanical 8/6/2024 Corrections Issued HERBERT GIRON
Underground Mechanical 8/12/2024 Approved HERBERT GIRON
HVAC-Rough 8/14/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 8/14/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 8/23/2024 Approved HERBERT GIRON
PLUMBING-Rough 9/3/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 9/17/2024 Corrections Issued HERBERT GIRON
HVAC-Rough 9/17/2024 Approved HERBERT GIRON
Deputy Wood Construction 9/18/2024 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 9/19/2024 Approved HERBERT GIRON
Special/Order Compliance 9/19/2024 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 9/23/2024 Corrections Issued HERBERT GIRON
Green Building Rough 9/23/2024 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 9/26/2024 Conditional Approval HERBERT GIRON
Green Building Rough 9/26/2024 Approved HERBERT GIRON
Insulation 9/26/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 9/26/2024 Partial Approval HERBERT GIRON
Drywall Nailing 10/7/2024 Approved REGINA MENDEZ
Interior/Exterior Lathing 10/22/2024 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 10/23/2024 Partial Approval HERBERT GIRON
Shower Pan 10/23/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 11/12/2024 Approved HERBERT GIRON
ELECTRICAL-Final 12/17/2024 Corrections Issued HERBERT GIRON
HVAC-Final 12/18/2024 Not Ready for Inspection HERBERT GIRON
PLUMBING-Final 12/18/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 1/15/2025 Corrections Issued HERBERT GIRON
PLUMBING-Final 1/15/2025 Partial Approval HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 1/15/2025 SGSOV Approved HERBERT GIRON
Shower Pan 2/20/2025 Approved HERBERT GIRON
Interior/Exterior Lathing 3/7/2025 Approved JAYLIN GRAVITTE
BUILDING-Rough-Frame 5/16/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 5/16/2025 Approved JESUS RODRIGUEZ
Final 5/16/2025 Partial Approval JESUS RODRIGUEZ
Green Building Final 5/16/2025 Approved JESUS RODRIGUEZ
HVAC-Final 5/16/2025 Approved JESUS RODRIGUEZ
PLUMBING-Final 5/16/2025 Approved JESUS RODRIGUEZ
Smoke Detectors 5/16/2025 Approved JESUS RODRIGUEZ