4135 S 11TH AVE 90008
Certificate Information: 4135 S 11TH AVE 90008
- Application / Permit
- 23014-10000-03220
- Plan Check / Job No.
- B23LA14963
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE FRONT PORCH, ADD BATH ROOM, LAUNDRY TO REAR OF EXISTING 1 STORY SINGLE FAMILY DEWLLING PER ENGINEER
- Permit Issued
- Issued on 1/16/2024
- Issuing Office
- Metro
- Current Status
- Issued on 1/16/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2023 | AUNG SOE |
| Corrections Issued | 8/22/2023 | AUNG SOE |
| Building Plans Picked Up | 8/24/2023 | APPLICANT |
| Plan Check Approved | 9/28/2023 | KHUONG TRUONG |
| Issued | 1/16/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/9/2023 | TERRY PHAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2023 | TERRY PHAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/29/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 11/22/2024 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2024 | Approved | BARRY HACHE |
| PLUMBING-Rough | 12/13/2024 | Approved | BARRY HACHE |
| Sewer | 12/13/2024 | Approved | BARRY HACHE |
| Insulation | 12/17/2024 | Partial Approval | ANTHONY RAMOS |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2024 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2025 | Partial Approval | LUIS CASTRO |
| Deputy Wood Construction | 1/16/2025 | Conditional Approval | ALEX COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 1/21/2025 | Approved | LUIS CASTRO |
| Gas Test | 1/28/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 1/28/2025 | Partial Approval | ANTHONY RAMOS |
| Shower Pan | 1/28/2025 | Approved | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 2/13/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 2/13/2025 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 2/13/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 2/13/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 2/13/2025 | Approved | LUIS CASTRO |
| Insulation | 2/18/2025 | Approved | LUIS CASTRO |
| Drywall Nailing | 2/20/2025 | Approved | LUIS CASTRO |
| Service/Power Release | 3/4/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 5/21/2025 | Partial Approval | LUIS CASTRO |
| Final | 5/21/2025 | Partial Inspection | LUIS CASTRO |
| Green Building Final | 5/21/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Final | 5/21/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 5/21/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 5/21/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 5/21/2025 | Not Ready for Inspection | LUIS CASTRO |