4135 S 11TH AVE 90008

Certificate Information: 4135 S 11TH AVE 90008

Application / Permit
23014-10000-03220
Plan Check / Job No.
B23LA14963
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE FRONT PORCH, ADD BATH ROOM, LAUNDRY TO REAR OF EXISTING 1 STORY SINGLE FAMILY DEWLLING PER ENGINEER
Permit Issued
Issued on 1/16/2024
Issuing Office
Metro
Current Status
Issued on 1/16/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/11/2023 APPLICANT
Assigned to Plan Check Engineer 8/18/2023 AUNG SOE
Corrections Issued 8/22/2023 AUNG SOE
Building Plans Picked Up 8/24/2023 APPLICANT
Plan Check Approved 9/28/2023 KHUONG TRUONG
Issued 1/16/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/9/2023 TERRY PHAN
Eng Process Fee Ord 176,300 Cleared 9/11/2023 TERRY PHAN

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/29/2024 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 11/22/2024 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Approved BARRY HACHE
PLUMBING-Rough 12/13/2024 Approved BARRY HACHE
Sewer 12/13/2024 Approved BARRY HACHE
Insulation 12/17/2024 Partial Approval ANTHONY RAMOS
Floor/Roof Diaphrgm/Shear Wall 12/19/2024 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 1/10/2025 Partial Approval LUIS CASTRO
Deputy Wood Construction 1/16/2025 Conditional Approval ALEX COLIN
Floor/Roof Diaphrgm/Shear Wall 1/21/2025 Approved LUIS CASTRO
PLUMBING-Rough 1/21/2025 Approved LUIS CASTRO
Gas Test 1/28/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 1/28/2025 Partial Approval ANTHONY RAMOS
Shower Pan 1/28/2025 Approved ANTHONY RAMOS
BUILDING-Rough-Frame 2/13/2025 Approved LUIS CASTRO
ELECTRICAL-Rough 2/13/2025 Partial Approval LUIS CASTRO
Green Building Rough 2/13/2025 Approved LUIS CASTRO
HVAC-Rough 2/13/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 2/13/2025 Approved LUIS CASTRO
Insulation 2/18/2025 Approved LUIS CASTRO
Drywall Nailing 2/20/2025 Approved LUIS CASTRO
Service/Power Release 3/4/2025 Approved LUIS CASTRO
ELECTRICAL-Final 5/21/2025 Partial Approval LUIS CASTRO
Final 5/21/2025 Partial Inspection LUIS CASTRO
Green Building Final 5/21/2025 Partial Approval LUIS CASTRO
HVAC-Final 5/21/2025 Approved LUIS CASTRO
PLUMBING-Final 5/21/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 5/21/2025 Not Ready for Inspection LUIS CASTRO