4307 N SUNNYSLOPE AVE 91423
Certificate Information: 4307 N SUNNYSLOPE AVE 91423
- Application / Permit
- 23014-10000-03215
- Plan Check / Job No.
- B23LA14933
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 14'-8" X 20'-10" ADDITION TO EXISTING SINGLE FAMILY DWELLING - PER WFPP
- Permit Issued
- Issued on 12/7/2023
- Issuing Office
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 8/30/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 9/20/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 10/20/2023 | KAMYAR EMAMI |
| Applicant returned to address corrections | 10/27/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 11/2/2023 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 11/3/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 11/20/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 12/6/2023 | DANIEL ABRAMYAN |
| Issued | 12/7/2023 | APPLICANT |
| CofO Issued | 9/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/8/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 9/8/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2023 | TAL SHEMEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/22/2024 | Conditional Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 2/22/2024 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 2/26/2024 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/26/2024 | Partial Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/3/2024 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 4/3/2024 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 5/20/2024 | Corrections Issued | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 5/28/2024 | Conditional Approval | DAVID MATSON |
| Deputy Wood Construction | 5/28/2024 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 6/3/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 6/3/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 6/10/2024 | Approved | JACK KARGODORIAN |
| Insulation | 6/25/2024 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 6/25/2024 | Approved | JOHN COLEMAN |
| Shower Pan | 6/25/2024 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 8/7/2024 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 8/7/2024 | Approved | MISAEL ESPARZA |
| Final | 8/7/2024 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/7/2024 | Approved | MISAEL ESPARZA |
| Green Building Final | 8/7/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 8/7/2024 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/7/2024 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 8/7/2024 | Corrections Issued | MISAEL ESPARZA |
| Final | 8/19/2024 | Conditional Approval | MISAEL ESPARZA |
| Green Building Final | 8/19/2024 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 8/19/2024 | Approved | MISAEL ESPARZA |