4307 N SUNNYSLOPE AVE 91423

Certificate Information: 4307 N SUNNYSLOPE AVE 91423

Application / Permit
23014-10000-03215
Plan Check / Job No.
B23LA14933
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
14'-8" X 20'-10" ADDITION TO EXISTING SINGLE FAMILY DWELLING - PER WFPP
Permit Issued
Issued on 12/7/2023
Issuing Office
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/29/2023 APPLICANT
Assigned to Plan Check Engineer 8/30/2023 DANIEL ABRAMYAN
Corrections Issued 8/30/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 9/20/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 10/20/2023 KAMYAR EMAMI
Applicant returned to address corrections 10/27/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 11/2/2023 GIOVANNY CHAVEZ
Applicant returned to address corrections 11/3/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 11/20/2023 DANIEL ABRAMYAN
Plan Check Approved 12/6/2023 DANIEL ABRAMYAN
Issued 12/7/2023 APPLICANT
CofO Issued 9/17/2024 DANIEL ORRANTE
Permit Finaled 9/17/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/8/2023 TAL SHEMEN
Sewer availability Cleared 9/8/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 9/11/2023 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/22/2024 Conditional Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 2/22/2024 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 2/26/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 2/26/2024 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 4/3/2024 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 4/3/2024 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 5/20/2024 Corrections Issued MISAEL ESPARZA
Deputy Drilled-In Anchors 5/28/2024 Conditional Approval DAVID MATSON
Deputy Wood Construction 5/28/2024 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 6/3/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 6/3/2024 Approved MISAEL ESPARZA
ELECTRICAL-Rough 6/10/2024 Approved JACK KARGODORIAN
Insulation 6/25/2024 Approved JOHN COLEMAN
Interior/Exterior Lathing 6/25/2024 Approved JOHN COLEMAN
Shower Pan 6/25/2024 Approved JOHN COLEMAN
BUILDING-Rough-Frame 8/7/2024 Approved MISAEL ESPARZA
Drywall Nailing 8/7/2024 Approved MISAEL ESPARZA
Final 8/7/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 8/7/2024 Approved MISAEL ESPARZA
Green Building Final 8/7/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 8/7/2024 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 8/7/2024 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 8/7/2024 Corrections Issued MISAEL ESPARZA
Final 8/19/2024 Conditional Approval MISAEL ESPARZA
Green Building Final 8/19/2024 Approved MISAEL ESPARZA
Smoke Detectors 8/19/2024 Approved MISAEL ESPARZA