1962 S POINT VIEW ST 90034

Certificate Information: 1962 S POINT VIEW ST 90034

Application / Permit
23014-10000-03214
Plan Check / Job No.
B23LA14922
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
**ePlan** Interior Remodel and rear Addtion to (E) Single Family Dwelling - 1 of 2 -
Permit Issued
Issued on 11/1/2023
Issuing Office
Current Status
CofO Issued on 9/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/11/2023 APPLICANT
Assigned to Plan Check Engineer 8/16/2023 EDWIN ESPIN
Corrections Issued 8/17/2023 EDWIN ESPIN
Plan Check Approved 9/11/2023 CAROLEAN BASMA
Issued 11/1/2023 APPLICANT
CofO in Progress 9/15/2025 ARTHUR NEGRETE
No Progress 9/18/2025 ARTHUR NEGRETE
CofO in Progress 9/18/2025 ARTHUR NEGRETE
Permit Finaled 9/21/2025 DEROLD HAUFF
CofO Issued 9/21/2025 DEROLD HAUFF
Permit Finaled 9/21/2025 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 8/23/2023 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 8/25/2023 AMBER CAMPBELL
Low Impact Development (LID) Cleared 8/28/2023 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/31/2023 AMBER CAMPBELL

Contact Information

Architect Ribeiro, De Moura, Ricardo Jorge; Lic. No.: NA38075       ,
Contractor Dragov Construction Group; Lic. No.: 1088785-B       ,
Engineer Ostowari,, Sohrab; Lic. No.: NA41014       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/8/2023 Approved JOSE AVILA
Footing/Foundation/Slab 11/15/2023 Approved JOSE AVILA
Deputy Drilled-In Anchors 11/16/2023 Conditional Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 1/12/2024 Partial Approval RONNIE MINDANAO
PLUMBING-Rough 1/12/2024 Partial Approval RONNIE MINDANAO
Insulation 1/17/2024 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 1/30/2024 Corrections Issued BRENDAN MORELLI
Interior/Exterior Lathing 1/30/2024 Not Ready for Inspection BRENDAN MORELLI
Shower Pan 1/30/2024 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Rough 2/8/2024 Approved STUART CHAPMAN
Green Building Rough 2/8/2024 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 2/8/2024 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 2/8/2024 Approved STUART CHAPMAN
HVAC-Rough 2/13/2024 Approved STUART CHAPMAN
BUILDING-Rough-Frame 2/16/2024 Approved STUART CHAPMAN
Green Building Rough 2/16/2024 Approved STUART CHAPMAN
Interior/Exterior Lathing 2/16/2024 Partial Approval STUART CHAPMAN
Insulation 3/6/2024 No Access for Inspection STUART CHAPMAN
Insulation 3/7/2024 Approved STUART CHAPMAN
Interior/Exterior Lathing 3/15/2024 Partial Approval STUART CHAPMAN
Shower Pan 3/15/2024 Approved STUART CHAPMAN
Drywall Nailing 3/28/2024 Approved STUART CHAPMAN
ELECTRICAL-Final 7/5/2024 Approved ARTHUR NEGRETE
Final 7/5/2024 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 7/5/2024 Corrections Issued ARTHUR NEGRETE
HVAC-Final 7/5/2024 Corrections Issued ARTHUR NEGRETE
PLUMBING-Final 7/5/2024 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 7/5/2024 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 7/5/2024 Approved ARTHUR NEGRETE
HVAC-Final 7/8/2024 Approved ARTHUR NEGRETE
Pre-Inspection 7/8/2024 Partial Approval ARTHUR NEGRETE
Final 3/14/2025 Partial Inspection ARTHUR NEGRETE
Green Building Final 3/14/2025 Not Ready for Inspection ARTHUR NEGRETE
Special/Order Compliance 3/14/2025 Partial Inspection ALEX COLIN
Final 8/19/2025 Conditional Approval ARTHUR NEGRETE
Green Building Final 8/19/2025 Approved ARTHUR NEGRETE
Final 9/15/2025 OK to Issue CofO ARTHUR NEGRETE