1962 S POINT VIEW ST 90034
Certificate Information: 1962 S POINT VIEW ST 90034
- Application / Permit
- 23014-10000-03214
- Plan Check / Job No.
- B23LA14922
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- **ePlan** Interior Remodel and rear Addtion to (E) Single Family Dwelling - 1 of 2 -
- Permit Issued
- Issued on 11/1/2023
- Issuing Office
- Current Status
- CofO Issued on 9/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2023 | EDWIN ESPIN |
| Corrections Issued | 8/17/2023 | EDWIN ESPIN |
| Plan Check Approved | 9/11/2023 | CAROLEAN BASMA |
| Issued | 11/1/2023 | APPLICANT |
| CofO in Progress | 9/15/2025 | ARTHUR NEGRETE |
| No Progress | 9/18/2025 | ARTHUR NEGRETE |
| CofO in Progress | 9/18/2025 | ARTHUR NEGRETE |
| Permit Finaled | 9/21/2025 | DEROLD HAUFF |
| CofO Issued | 9/21/2025 | DEROLD HAUFF |
| Permit Finaled | 9/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/23/2023 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2023 | AMBER CAMPBELL |
| Low Impact Development (LID) | Cleared | 8/28/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/31/2023 | AMBER CAMPBELL |
Contact Information
| Architect | Ribeiro, De Moura, Ricardo Jorge; Lic. No.: NA38075 | , |
| Contractor | Dragov Construction Group; Lic. No.: 1088785-B | , |
| Engineer | Ostowari,, Sohrab; Lic. No.: NA41014 | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/8/2023 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 11/15/2023 | Approved | JOSE AVILA |
| Deputy Drilled-In Anchors | 11/16/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2024 | Partial Approval | RONNIE MINDANAO |
| PLUMBING-Rough | 1/12/2024 | Partial Approval | RONNIE MINDANAO |
| Insulation | 1/17/2024 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2024 | Corrections Issued | BRENDAN MORELLI |
| Interior/Exterior Lathing | 1/30/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Shower Pan | 1/30/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| ELECTRICAL-Rough | 2/8/2024 | Approved | STUART CHAPMAN |
| Green Building Rough | 2/8/2024 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 2/8/2024 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 2/8/2024 | Approved | STUART CHAPMAN |
| HVAC-Rough | 2/13/2024 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 2/16/2024 | Approved | STUART CHAPMAN |
| Green Building Rough | 2/16/2024 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 2/16/2024 | Partial Approval | STUART CHAPMAN |
| Insulation | 3/6/2024 | No Access for Inspection | STUART CHAPMAN |
| Insulation | 3/7/2024 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 3/15/2024 | Partial Approval | STUART CHAPMAN |
| Shower Pan | 3/15/2024 | Approved | STUART CHAPMAN |
| Drywall Nailing | 3/28/2024 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 7/5/2024 | Approved | ARTHUR NEGRETE |
| Final | 7/5/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 7/5/2024 | Corrections Issued | ARTHUR NEGRETE |
| HVAC-Final | 7/5/2024 | Corrections Issued | ARTHUR NEGRETE |
| PLUMBING-Final | 7/5/2024 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 7/5/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 7/5/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 7/8/2024 | Approved | ARTHUR NEGRETE |
| Pre-Inspection | 7/8/2024 | Partial Approval | ARTHUR NEGRETE |
| Final | 3/14/2025 | Partial Inspection | ARTHUR NEGRETE |
| Green Building Final | 3/14/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Special/Order Compliance | 3/14/2025 | Partial Inspection | ALEX COLIN |
| Final | 8/19/2025 | Conditional Approval | ARTHUR NEGRETE |
| Green Building Final | 8/19/2025 | Approved | ARTHUR NEGRETE |
| Final | 9/15/2025 | OK to Issue CofO | ARTHUR NEGRETE |