4228 W AVENUE 40 90065
Certificate Information: 4228 W AVENUE 40 90065
- Application / Permit
- 23014-10000-03209
- Plan Check / Job No.
- B23LA14883
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Ground Floor Addition to (E) Garage to have ADU Per Ca Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 10/31/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 8/24/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 9/1/2023 | KEN GILL |
| Applicant returned to address corrections | 10/4/2023 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 10/17/2023 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 10/31/2023 | MAHNAZ NOURHASHEMI |
| Issued | 10/31/2023 | APPLICANT |
| CofO in Progress | 10/9/2024 | ROY SPAULDING |
| CofO Issued | 11/1/2024 | DEROLD HAUFF |
| Permit Finaled | 11/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/28/2023 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2023 | JESSICA OPINION |
| Sewer availability | Cleared | 9/6/2023 | JESSICA OPINION |
| Hydrant and Access approval | Cleared | 9/23/2023 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 10/17/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/18/2023 | JUSTIN BICOL |
| Supp. Use District POD/CDO/TDO | Cleared | 10/19/2023 | ANDREA MAGANA-WITHERS |
| GPI Written Notices | Cleared | 10/31/2023 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 10/31/2023 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mendoza,, Fabian; Lic. No.: C90183 | PO BOX 2305 NORWALK, CA 90651 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 11/2/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 11/2/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 11/2/2023 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 11/2/2023 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 11/2/2023 | Corrections Issued | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 11/3/2023 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Partial Approval | BRIAN SULLIVAN |
| Pre-Inspection | 11/16/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 11/27/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 11/27/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Gas Test | 11/27/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Rough | 11/27/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 11/27/2023 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 11/27/2023 | Approved | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 11/28/2023 | Conditional Approval | ROY SPAULDING |
| PLUMBING-Rough | 11/30/2023 | Approved | ROY SPAULDING |
| Underground Mechanical | 11/30/2023 | Not Ready for Inspection | ROY SPAULDING |
| BUILDING-Rough-Frame | 12/8/2023 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 12/8/2023 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 12/8/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 12/8/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 12/15/2023 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 12/28/2023 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 1/2/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 1/10/2024 | Approved | CRAIG VAUGHAN |
| Shower Pan | 1/10/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/28/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/29/2024 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/26/2024 | Approved | ROY SPAULDING |
| Final | 9/26/2024 | Corrections Issued | ROY SPAULDING |
| Footing/Foundation/Slab | 9/26/2024 | Approved | ROY SPAULDING |
| Green Building Final | 9/26/2024 | Approved | ROY SPAULDING |
| MERV13>=Final | 9/26/2024 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 9/26/2024 | SGSOV Not Ready | ROY SPAULDING |
| Smoke Detectors | 9/26/2024 | Not Ready for Inspection | ROY SPAULDING |
| Final | 10/3/2024 | Corrections Issued | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 10/3/2024 | SGSOV Not Ready | ROY SPAULDING |
| Smoke Detectors | 10/3/2024 | Approved | ROY SPAULDING |
| Final | 10/8/2024 | OK to Issue CofO | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 10/8/2024 | SGSOV Approved | ROY SPAULDING |