1061 E AMOROSO PL 90291

Certificate Information: 1061 E AMOROSO PL 90291

Application / Permit
23014-10000-03183
Plan Check / Job No.
B23LA14787
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODELING AND 2ND STORY ADDITION TO SFD WITH ATTACHED 2-CAR GARAGE. NFPA 13D SPRINKLERED THROUGH OUT "COMPLY WITH DERPARTMENT ORDER EFFECTIVE 12/11/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 12/26/2023
Issuing Office
Metro
Current Status
Issued on 12/26/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/9/2023 APPLICANT
Assigned to Plan Check Engineer 8/24/2023 JAD BASMA
Corrections Issued 9/1/2023 JAD BASMA
Quality Review Completed 9/1/2023 KEN GILL
Building Plans Picked Up 9/5/2023 APPLICANT
Applicant returned to address corrections 12/8/2023 JAD BASMA
Plan Check Approved 12/14/2023 JAD BASMA
No Progress 12/14/2023 JAD BASMA
Plan Check Approved 12/14/2023 JAD BASMA
No Progress 12/14/2023 JAD BASMA
Plan Check Approved 12/14/2023 JAD BASMA
Issued 12/26/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/25/2023 ANDREA SAINT-ANTONIN
Sewer availability Cleared 10/25/2023 ANDREA SAINT-ANTONIN
Low Impact Development (LID) Cleared 11/16/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 11/20/2023 AHMED AMARRAGY
Specific Plan Cleared 12/13/2023 ALESSANDRO MERCURI
Hold Cleared 2/7/2024 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/15/2024 Approved RYAN BARNES
Footing/Foundation/Slab 2/15/2024 Conditional Approval RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Conditional Approval RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 4/30/2024 Approved RYAN BARNES
PLUMBING-Rough 5/2/2024 Partial Approval RYAN BARNES
Rough-Elec/Plmb/HVAC 5/20/2024 Partial Approval RYAN BARNES
Gas Test 6/7/2024 Approved RYAN BARNES
PLUMBING-Rough 6/7/2024 Approved RYAN BARNES
Sewer 6/7/2024 Approved RYAN BARNES
Deputy Wood Construction 6/25/2024 Approved RYAN BARNES
ELECTRICAL-Rough 6/25/2024 Corrections Issued RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 6/25/2024 Approved RYAN BARNES
HVAC-Rough 6/25/2024 Approved RYAN BARNES
Interior/Exterior Lathing 6/25/2024 Partial Approval RYAN BARNES
ELECTRICAL-Rough 6/26/2024 Approved RYAN BARNES
PLUMBING-Rough 7/8/2024 Partial Approval JOHN MATTILLO
Interior/Exterior Lathing 7/18/2024 Approved JOHN MATTILLO
Insulation 7/29/2024 Approved RYAN BARNES
Shower Pan 7/29/2024 Approved RYAN BARNES
Drywall Nailing 8/26/2024 Approved RYAN BARNES
Interior/Exterior Lathing 10/1/2024 Approved RYAN BARNES
BUILDING-Rough-Frame 9/29/2025 Approved RYAN BARNES
Final 9/29/2025 Not Ready for Inspection RYAN BARNES
Footing/Foundation/Slab 9/29/2025 Approved RYAN BARNES
Green Building Final 9/29/2025 Approved RYAN BARNES
Green Building Rough 9/29/2025 Approved RYAN BARNES
SGSOV-Seismic Gas S/O Valve 9/29/2025 SGSOV Approved RYAN BARNES
Smoke Detectors 9/29/2025 Approved RYAN BARNES
Final 10/20/2025 Conditional Approval RYAN BARNES