13651 W PINNEY ST 91331
Certificate Information: 13651 W PINNEY ST 91331
- Application / Permit
- 23014-10000-03175
- Plan Check / Job No.
- B23LA14773
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion with Addition of (E) Recreation Room/Storage to an Accessory Dwelling Unit with Storage per LAMC 12.22 A.33 (c)-(d) .
- Permit Issued
- Issued on 12/21/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/14/2023 | MICHAEL LANZONE |
| Corrections Issued | 8/14/2023 | MICHAEL LANZONE |
| Building Plans Picked Up | 8/16/2023 | APPLICANT |
| Applicant returned to address corrections | 12/7/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 12/11/2023 | ADAM HEGAZI |
| Issued | 12/21/2023 | APPLICANT |
| CofO in Progress | 7/12/2024 | MICHEL ABAJAN |
| CofO Issued | 7/23/2024 | RUBEN SALAS |
| Permit Finaled | 7/23/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/19/2023 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 8/19/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 10/6/2023 | COLIN LOREDO |
Contact Information
| Contractor | Tizcareno'S Unlimited Construction; Lic. No.: 953087-B | 14338 TIARA STREET SHERMAN OAKS, CA 91401 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/28/2023 | Conditional Approval | ROBERT GOLD |
| METHANE-Subgrade | 1/5/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 1/5/2024 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 1/9/2024 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 1/9/2024 | Approved | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 2/1/2024 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 2/27/2024 | Partial Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2024 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 2/27/2024 | Partial Inspection | MICHEL ABAJAN |
| METHANE-Rough | 2/27/2024 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/15/2024 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 3/15/2024 | Corrections Issued | KEVIN BERBERYAN |
| Sewer | 3/15/2024 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 3/15/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 3/19/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/19/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/28/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 3/28/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 3/28/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/28/2024 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 3/28/2024 | Approved | MICHEL ABAJAN |
| Insulation | 4/1/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 4/15/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/15/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/5/2024 | Approved | MICHEL ABAJAN |
| Final | 7/5/2024 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/5/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/5/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/5/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/5/2024 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 7/5/2024 | Approved | MICHEL ABAJAN |
| Final | 7/12/2024 | OK to Issue CofO | MICHEL ABAJAN |