13651 W PINNEY ST 91331

Certificate Information: 13651 W PINNEY ST 91331

Application / Permit
23014-10000-03175
Plan Check / Job No.
B23LA14773
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion with Addition of (E) Recreation Room/Storage to an Accessory Dwelling Unit with Storage per LAMC 12.22 A.33 (c)-(d) .
Permit Issued
Issued on 12/21/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2023 APPLICANT
Assigned to Plan Check Engineer 8/14/2023 MICHAEL LANZONE
Corrections Issued 8/14/2023 MICHAEL LANZONE
Building Plans Picked Up 8/16/2023 APPLICANT
Applicant returned to address corrections 12/7/2023 JOSEPH RAFOLS
Plan Check Approved 12/11/2023 ADAM HEGAZI
Issued 12/21/2023 APPLICANT
CofO in Progress 7/12/2024 MICHEL ABAJAN
CofO Issued 7/23/2024 RUBEN SALAS
Permit Finaled 7/23/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/19/2023 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 8/19/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 10/6/2023 COLIN LOREDO
Sewer availability Cleared 10/6/2023 COLIN LOREDO

Contact Information

Contractor Tizcareno'S Unlimited Construction; Lic. No.: 953087-B 14338 TIARA STREET      SHERMAN OAKS, CA 91401

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/28/2023 Conditional Approval ROBERT GOLD
METHANE-Subgrade 1/5/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 1/5/2024 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 1/9/2024 Approved MICHEL ABAJAN
METHANE-Barrier 1/9/2024 Approved MICHEL ABAJAN
Deputy Drilled-In Anchors 2/1/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 2/27/2024 Partial Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/27/2024 Partial Approval MICHEL ABAJAN
Green Building Rough 2/27/2024 Partial Inspection MICHEL ABAJAN
METHANE-Rough 2/27/2024 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Rough 3/15/2024 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 3/15/2024 Corrections Issued KEVIN BERBERYAN
Sewer 3/15/2024 Approved KEVIN BERBERYAN
Underground Mechanical 3/15/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 3/19/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 3/19/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/28/2024 Approved MICHEL ABAJAN
Green Building Rough 3/28/2024 Approved MICHEL ABAJAN
HVAC-Rough 3/28/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/28/2024 Approved MICHEL ABAJAN
METHANE-Rough 3/28/2024 Approved MICHEL ABAJAN
Insulation 4/1/2024 Approved MICHEL ABAJAN
Drywall Nailing 4/15/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/15/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 7/5/2024 Approved MICHEL ABAJAN
Final 7/5/2024 Corrections Issued MICHEL ABAJAN
Green Building Final 7/5/2024 Approved MICHEL ABAJAN
HVAC-Final 7/5/2024 Approved MICHEL ABAJAN
PLUMBING-Final 7/5/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/5/2024 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 7/5/2024 Approved MICHEL ABAJAN
Final 7/12/2024 OK to Issue CofO MICHEL ABAJAN