245 1/2 E 109TH ST 90061

Certificate Information: 245 1/2 E 109TH ST 90061

Application / Permit
23014-10000-03148
Plan Check / Job No.
B23LA14637
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT (E) DETACHED GARAGE AND STORAGE AND (N) IRREG. 8'-7" X 11'-4 3/4" ADDITION TO ADU PER LAMC 12.22 A.33(c) and (d). WORK PER WFPP.
Permit Issued
Issued on 9/19/2023
Issuing Office
Current Status
CofO Issued on 4/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/7/2023 APPLICANT
Assigned to Plan Check Engineer 8/11/2023 ISIS ARGUETA
Corrections Issued 8/11/2023 ISIS ARGUETA
Applicant returned to address corrections 9/7/2023 ISIS ARGUETA
Plan Check Approved 9/13/2023 ISIS ARGUETA
Plan Check Approved 9/19/2023 ISIS ARGUETA
Issued 9/19/2023 APPLICANT
CofO in Progress 4/3/2025 ANTHONY EGSON
CofO in Progress 4/15/2025 JOSEPH MCGARRY
Permit Finaled 4/15/2025 ANSON MAGLASANG
CofO Issued 4/15/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 8/16/2023 FRANK SALAZAR
Roof/Waste drainage to street Cleared 8/16/2023 FRANK SALAZAR
Eng Process Fee Ord 176,300 Cleared 9/6/2023 FRANK SALAZAR
Sewer availability Cleared 9/12/2023 FRANK SALAZAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 11/3/2023 Not Ready for Inspection JOHN KLARIN
Footing/Foundation/Slab 11/3/2023 Corrections Issued JOHN KLARIN
Green Building Rough 11/3/2023 Not Ready for Inspection JOHN KLARIN
Deputy Drilled-In Anchors 11/7/2023 Approved JOHN KLARIN
Footing/Foundation/Slab 11/16/2023 Approved JOHN KLARIN
Sewer 12/1/2023 Approved JAMES CHAVEZ
Underground Mechanical 12/1/2023 Partial Approval JAMES CHAVEZ
BUILDING-Rough-Frame 12/21/2023 Corrections Issued JOHN KLARIN
Green Building Rough 12/21/2023 Not Ready for Inspection JOHN KLARIN
Wood Frame 12/21/2023 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 12/27/2023 Not Ready for Inspection JOHN KLARIN
Green Building Rough 12/27/2023 Not Ready for Inspection JOHN KLARIN
Rough-Elec/Plmb/HVAC 4/26/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 5/6/2024 Corrections Issued JAMES CHAVEZ
PLUMBING-Rough 5/6/2024 Approved JAMES CHAVEZ
ELECTRICAL-Rough 5/9/2024 Approved BEN MOLSTAD
PLUMBING-Rough 5/9/2024 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 5/16/2024 Partial Approval BEN MOLSTAD
Wood Frame 5/16/2024 Not Ready for Inspection BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 5/30/2024 Corrections Issued BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 6/5/2024 Partial Approval BEN MOLSTAD
HVAC-Rough 6/13/2024 Corrections Issued BEN MOLSTAD
Gas Test 6/21/2024 Approved BEN MOLSTAD
HVAC-Final 6/21/2024 Corrections Issued BEN MOLSTAD
Interior/Exterior Lathing 7/5/2024 Not Ready for Inspection EUGENE CASSIDY
Special/Order Compliance 7/5/2024 Corrections Issued EUGENE CASSIDY
Insulation 7/25/2024 No Access for Inspection BEN MOLSTAD
Insulation 7/26/2024 Corrections Issued BEN MOLSTAD
HVAC-Final 8/9/2024 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 8/9/2024 Partial Approval BEN MOLSTAD
Special/Order Compliance 8/9/2024 Partial Inspection BARRY HACHE
ELECTRICAL-Final 8/19/2024 Not Ready for Inspection BEN MOLSTAD
Insulation 8/19/2024 Approved BEN MOLSTAD
Special/Order Compliance 8/19/2024 Partial Inspection BARRY HACHE
Gas Test 8/26/2024 Approved BARRY HACHE
Special/Order Compliance 8/26/2024 Partial Approval BEN MOLSTAD
Drywall Nailing 8/29/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Final 8/29/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 8/29/2024 Approved BEN MOLSTAD
Insulation 8/29/2024 Approved BEN MOLSTAD
Interior/Exterior Lathing 8/29/2024 Partial Approval BEN MOLSTAD
Rough-Elec/Plmb/HVAC 8/29/2024 Approved BEN MOLSTAD
Service/Power Release 8/29/2024 Not Ready for Inspection BEN MOLSTAD
Drywall Nailing 9/6/2024 Approved BEN MOLSTAD
Interior/Exterior Lathing 9/6/2024 Partial Approval BEN MOLSTAD
BUILDING-Rough-Frame 11/15/2024 No Access for Inspection ANTHONY EGSON
ELECTRICAL-Final 11/15/2024 No Access for Inspection ANTHONY EGSON
Final 11/15/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Final 11/15/2024 No Access for Inspection ANTHONY EGSON
Green Building Rough 11/15/2024 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 11/15/2024 No Access for Inspection ANTHONY EGSON
PLUMBING-Final 11/15/2024 No Access for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 11/15/2024 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 11/15/2024 No Access for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 11/20/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 11/20/2024 Corrections Issued ANTHONY EGSON
Final 11/20/2024 Corrections Issued ANTHONY EGSON
Green Building Final 11/20/2024 Corrections Issued ANTHONY EGSON
Green Building Rough 11/20/2024 Approved ANTHONY EGSON
HVAC-Final 11/20/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Final 11/20/2024 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 11/20/2024 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 11/20/2024 Corrections Issued ANTHONY EGSON
Special/Order Compliance 11/21/2024 Corrections Issued ANTHONY EGSON
Final 12/30/2024 Corrections Issued ANTHONY EGSON
Green Building Final 12/30/2024 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 12/30/2024 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 12/30/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 1/24/2025 Approved ANTHONY EGSON
Final 1/24/2025 Corrections Issued ANTHONY EGSON
Green Building Final 1/24/2025 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 1/24/2025 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 1/24/2025 SGSOV Not Ready ANTHONY EGSON
Gas Test 1/28/2025 Approved ANTHONY EGSON
Final 2/7/2025 Corrections Issued BEN MOLSTAD
Green Building Final 2/7/2025 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 2/7/2025 SGSOV Approved BEN MOLSTAD
Final 2/19/2025 Corrections Issued ANTHONY EGSON
Green Building Final 2/19/2025 Corrections Issued ANTHONY EGSON
Final 2/28/2025 Corrections Issued BEN MOLSTAD
Green Building Final 2/28/2025 Partial Approval BEN MOLSTAD
Final 3/11/2025 Not Ready for Inspection ANTHONY EGSON
Green Building Final 3/11/2025 Corrections Issued ANTHONY EGSON
Final 4/2/2025 OK to Issue CofO ANTHONY EGSON
Green Building Final 4/2/2025 Approved ANTHONY EGSON
Final 4/14/2025 OK to Issue CofO JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 4/14/2025 SGSOV Approved JOSEPH MCGARRY