245 1/2 E 109TH ST 90061
Certificate Information: 245 1/2 E 109TH ST 90061
- Application / Permit
- 23014-10000-03148
- Plan Check / Job No.
- B23LA14637
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT (E) DETACHED GARAGE AND STORAGE AND (N) IRREG. 8'-7" X 11'-4 3/4" ADDITION TO ADU PER LAMC 12.22 A.33(c) and (d). WORK PER WFPP.
- Permit Issued
- Issued on 9/19/2023
- Issuing Office
- Current Status
- CofO Issued on 4/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2023 | ISIS ARGUETA |
| Corrections Issued | 8/11/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 9/7/2023 | ISIS ARGUETA |
| Plan Check Approved | 9/13/2023 | ISIS ARGUETA |
| Plan Check Approved | 9/19/2023 | ISIS ARGUETA |
| Issued | 9/19/2023 | APPLICANT |
| CofO in Progress | 4/3/2025 | ANTHONY EGSON |
| CofO in Progress | 4/15/2025 | JOSEPH MCGARRY |
| Permit Finaled | 4/15/2025 | ANSON MAGLASANG |
| CofO Issued | 4/15/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 8/16/2023 | FRANK SALAZAR |
| Roof/Waste drainage to street | Cleared | 8/16/2023 | FRANK SALAZAR |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2023 | FRANK SALAZAR |
| Sewer availability | Cleared | 9/12/2023 | FRANK SALAZAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/3/2023 | Not Ready for Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 11/3/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 11/3/2023 | Not Ready for Inspection | JOHN KLARIN |
| Deputy Drilled-In Anchors | 11/7/2023 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 11/16/2023 | Approved | JOHN KLARIN |
| Sewer | 12/1/2023 | Approved | JAMES CHAVEZ |
| Underground Mechanical | 12/1/2023 | Partial Approval | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 12/21/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 12/21/2023 | Not Ready for Inspection | JOHN KLARIN |
| Wood Frame | 12/21/2023 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 12/27/2023 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 12/27/2023 | Not Ready for Inspection | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 4/26/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 5/6/2024 | Corrections Issued | JAMES CHAVEZ |
| PLUMBING-Rough | 5/6/2024 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 5/9/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 5/9/2024 | Approved | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2024 | Partial Approval | BEN MOLSTAD |
| Wood Frame | 5/16/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2024 | Corrections Issued | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2024 | Partial Approval | BEN MOLSTAD |
| HVAC-Rough | 6/13/2024 | Corrections Issued | BEN MOLSTAD |
| Gas Test | 6/21/2024 | Approved | BEN MOLSTAD |
| HVAC-Final | 6/21/2024 | Corrections Issued | BEN MOLSTAD |
| Interior/Exterior Lathing | 7/5/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Special/Order Compliance | 7/5/2024 | Corrections Issued | EUGENE CASSIDY |
| Insulation | 7/25/2024 | No Access for Inspection | BEN MOLSTAD |
| Insulation | 7/26/2024 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 8/9/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 8/9/2024 | Partial Approval | BEN MOLSTAD |
| Special/Order Compliance | 8/9/2024 | Partial Inspection | BARRY HACHE |
| ELECTRICAL-Final | 8/19/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 8/19/2024 | Approved | BEN MOLSTAD |
| Special/Order Compliance | 8/19/2024 | Partial Inspection | BARRY HACHE |
| Gas Test | 8/26/2024 | Approved | BARRY HACHE |
| Special/Order Compliance | 8/26/2024 | Partial Approval | BEN MOLSTAD |
| Drywall Nailing | 8/29/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 8/29/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 8/29/2024 | Approved | BEN MOLSTAD |
| Insulation | 8/29/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 8/29/2024 | Partial Approval | BEN MOLSTAD |
| Rough-Elec/Plmb/HVAC | 8/29/2024 | Approved | BEN MOLSTAD |
| Service/Power Release | 8/29/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Drywall Nailing | 9/6/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 9/6/2024 | Partial Approval | BEN MOLSTAD |
| BUILDING-Rough-Frame | 11/15/2024 | No Access for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 11/15/2024 | No Access for Inspection | ANTHONY EGSON |
| Final | 11/15/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 11/15/2024 | No Access for Inspection | ANTHONY EGSON |
| Green Building Rough | 11/15/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 11/15/2024 | No Access for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 11/15/2024 | No Access for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 11/15/2024 | No Access for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/20/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 11/20/2024 | Corrections Issued | ANTHONY EGSON |
| Final | 11/20/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 11/20/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 11/20/2024 | Approved | ANTHONY EGSON |
| HVAC-Final | 11/20/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 11/20/2024 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 11/20/2024 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 11/20/2024 | Corrections Issued | ANTHONY EGSON |
| Special/Order Compliance | 11/21/2024 | Corrections Issued | ANTHONY EGSON |
| Final | 12/30/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 12/30/2024 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 12/30/2024 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 12/30/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 1/24/2025 | Approved | ANTHONY EGSON |
| Final | 1/24/2025 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 1/24/2025 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 1/24/2025 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/24/2025 | SGSOV Not Ready | ANTHONY EGSON |
| Gas Test | 1/28/2025 | Approved | ANTHONY EGSON |
| Final | 2/7/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 2/7/2025 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 2/7/2025 | SGSOV Approved | BEN MOLSTAD |
| Final | 2/19/2025 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 2/19/2025 | Corrections Issued | ANTHONY EGSON |
| Final | 2/28/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 2/28/2025 | Partial Approval | BEN MOLSTAD |
| Final | 3/11/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 3/11/2025 | Corrections Issued | ANTHONY EGSON |
| Final | 4/2/2025 | OK to Issue CofO | ANTHONY EGSON |
| Green Building Final | 4/2/2025 | Approved | ANTHONY EGSON |
| Final | 4/14/2025 | OK to Issue CofO | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 4/14/2025 | SGSOV Approved | JOSEPH MCGARRY |