2804 S HOLT AVE 90034

Certificate Information: 2804 S HOLT AVE 90034

Application / Permit
23014-10000-03131
Plan Check / Job No.
B23LA14597
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERSION AND ADDITION TO (E) DETACHED 1-STORY GARAGE. TO BE CONVERTED INTO PROPOSED REC ROOM & STORAGE AT LOWER LEVEL AND NEW ADU (ADDITION) AT 2ND LEVEL. DETACHED ADU PER 66323(a).
Permit Issued
Issued on 9/26/2025
Issuing Office
Current Status
Issued on 9/26/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/30/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 ADRIANA LOPEZ
Corrections Issued 9/21/2023 ADRIANA LOPEZ
Quality Review Completed 9/29/2023 GARO TELMI
Applicant returned to address corrections 2/15/2024 ADRIANA LOPEZ
Applicant returned to address corrections 5/21/2025 ADRIANA LOPEZ
Applicant returned to address corrections 8/5/2025 ADRIANA LOPEZ
Applicant returned to address corrections 8/21/2025 ADRIANA LOPEZ
Plan Check Approved 8/27/2025 ADRIANA LOPEZ
Issued 9/26/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/18/2023 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 3/10/2025 DAVID LOPEZ
Sewer availability Cleared 3/10/2025 DAVID LOPEZ
Low Impact Development (LID) Cleared 3/19/2025 LUIS LUVANO
Roof/Waste drainage to street Cleared 3/20/2025 DAVID LOPEZ

Contact Information

Contractor Adu Rc Builders; Lic. No.: 1080967-B       ,
Contractor Ca Construction Group Inc; Lic. No.: 1080967-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/5/2025 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 12/12/2025 Approved EVAN COOPER
Footing/Foundation/Slab 12/12/2025 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 1/21/2026 Partial Approval WILBER ROSALES
BUILDING-Rough-Frame 4/14/2026 Not Ready for Inspection WILBER ROSALES
Deputy Wood Construction 4/14/2026 Conditional Approval WILBER ROSALES
ELECTRICAL-Rough 4/14/2026 Corrections Issued WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 4/14/2026 Corrections Issued WILBER ROSALES
Green Building Rough 4/14/2026 Not Ready for Inspection WILBER ROSALES
HVAC-Rough 4/14/2026 Approved WILBER ROSALES
MERV13>=Rough 4/14/2026 Not Ready for Inspection WILBER ROSALES
PLUMBING-Rough 4/14/2026 Not Ready for Inspection WILBER ROSALES
BUILDING-Rough-Frame 5/5/2026 Partial Approval WILBER ROSALES
ELECTRICAL-Rough 5/5/2026 Partial Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 5/5/2026 Approved WILBER ROSALES
Green Building Rough 5/5/2026 Approved WILBER ROSALES
Interior/Exterior Lathing 5/5/2026 Partial Approval WILBER ROSALES
MERV13>=Rough 5/5/2026 Approved WILBER ROSALES
PLUMBING-Rough 5/5/2026 Approved WILBER ROSALES
Insulation 5/13/2026 Partial Approval DANIEL VERA