968-970 W 43RD ST 90037

Certificate Information: 968-970 W 43RD ST 90037

Application / Permit
23014-10000-03118
Plan Check / Job No.
B23LA14535
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
PROPOSE 2ND STORY ADDITION AT REAR OF EXISITNG DUPLEX.
Permit Issued
Issued on 10/9/2024
Issuing Office
Metro
Current Status
CofO Issued on 9/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2023 APPLICANT
Assigned to Plan Check Engineer 8/22/2023 NGHI SU
Corrections Issued 8/22/2023 NGHI SU
Quality Review Completed 8/22/2023 KEN GILL
Building Plans Picked Up 8/28/2023 APPLICANT
Plan Check Approved 10/3/2024 NGHI SU
Issued 10/9/2024 APPLICANT
CofO in Progress 9/12/2025 SABAS ALONSO
Permit Finaled 9/13/2025 DEROLD HAUFF
CofO Issued 9/13/2025 DEROLD HAUFF
Permit Finaled 9/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/16/2024 TREVOR QUAN
Sewer availability Cleared 5/30/2024 TREVOR QUAN
Low Impact Development (LID) Cleared 8/24/2024 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 9/5/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 9/9/2024 TREVOR QUAN
Tenant Habitability Plan Cleared 9/26/2024 RICARDO BOHORQUEZ
"Q" conditions Cleared 9/27/2024 JAZMIN ROQUE

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez,, Jose Antonio; Lic. No.: C69472 3557 E 58TH ST      MAYWOOD, CA 90270
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/13/2024 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 12/2/2024 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/27/2024 Corrections Issued SABAS ALONSO
Deputy Drilled-In Anchors 1/10/2025 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/10/2025 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 1/10/2025 Approved SABAS ALONSO
Underground Mechanical 1/10/2025 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 1/24/2025 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/24/2025 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 1/24/2025 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 1/28/2025 No Access for Inspection BARRY HACHE
HVAC-Rough 1/28/2025 No Access for Inspection BARRY HACHE
PLUMBING-Rough 1/28/2025 No Access for Inspection BARRY HACHE
ELECTRICAL-Rough 1/29/2025 Corrections Issued SABAS ALONSO
HVAC-Rough 1/29/2025 Corrections Issued SABAS ALONSO
PLUMBING-Rough 1/29/2025 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 2/7/2025 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 2/7/2025 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 2/7/2025 Partial Approval SABAS ALONSO
PLUMBING-Rough 2/7/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 2/26/2025 Conditional Approval SABAS ALONSO
Green Building Rough 2/26/2025 Approved SABAS ALONSO
HVAC-Rough 2/26/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 3/6/2025 Approved SABAS ALONSO
Insulation 3/6/2025 Approved SABAS ALONSO
Drywall Nailing 3/11/2025 Corrections Issued ANTHONY RAMOS
Drywall Nailing 3/13/2025 Approved SABAS ALONSO
Final 6/11/2025 Corrections Issued SABAS ALONSO
Green Building Final 6/11/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/11/2025 SGSOV Approved SABAS ALONSO
Smoke Detectors 6/11/2025 Approved SABAS ALONSO
Final 9/11/2025 OK to Issue CofO SABAS ALONSO